EFW Group Ltd v Secretary of State for Business, Energy and Industrial Strategy

JurisdictionEngland & Wales
JudgeMr Justice Dove
Judgment Date08 October 2021
Neutral Citation[2021] EWHC 2697 (Admin)
Docket NumberCase No: CO/1160/2021
CourtQueen's Bench Division (Administrative Court)

[2021] EWHC 2697 (Admin)

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

Royal Courts of Justice

Strand, London, WC2A 2LL

Before:

THE HONOURABLE Mr Justice Dove

Case No: CO/1160/2021

Between:
EFW Group Limited
Claimant
and
Secretary of State for Business, Energy and Industrial Strategy
Defendant

Michael Humphries QC and Mark Westmoreland Smith (instructed by Keystone Law) for the Claimant

Ned Westaway (instructed by Government Legal Department) for the Defendant

Hearing dates: 13 th and 14 th July 2021

Approved Judgment

I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.

Mr Justice Dove Mr Justice Dove
1

This is an application for judicial review pursuant to section 118 of the Planning Act 2008 (“the 2008 Act”) seeking to quash the defendant's decision dated 19 th February 2021. The application before the defendant included two separate and discrete proposals. The first proposal was for the Wheelebrator Kemsley North (“WKN”) and the second was for the Wheelebrator Kemsley K3 (“K3”), both of which were proposals for energy from waste described in greater detail below. Whilst the name of the claimant company changed between the determination of the application and the commencement of these proceedings nothing turns on the fact that the claimant's name has altered.

The Facts

2

The claimant is the developer and operator of a pre-existing waste-to-energy plant at Kemsley, Kent which was granted planning permission on 14 th June 2019 and has been fully built out (“the Kemsley plant”). It supplies heat to an adjacent paper mill, and has permitted capacity of up to 49.9MW with a waste throughput of 550,000 tonnes per annum. It was commissioned in July 2020.

3

The claimant contemplated two further development projects. Firstly, K3, which amounted to a proposal to increase the generating capacity of the consented Kemsley plant from 49.9MW to 75MW, and increase the total waste tonnage throughput from 550,000 to 657,000 tonnes per annum. This project simply involved an increase in the permitted capacities of the facility and did not require any physical works in order to achieve them. The second proposal was WKN, which was a new waste-to-energy facility capable of processing 390,000 tonnes of waste and generating 42MW of electricity. WKN was intended to supply energy to the adjacent paper mill when the Kemsley plant was offline for maintenance and was designed to be combined heat and power (“CHP”) ready in order to take advantage of any future developments. The K3 project fell within the definition of a nationally significant infrastructure project (“NSIP”) as defined by section 15 of the 2008 Act (which is dealt with in greater detail below), on the basis that the final capacity for the Kemsley plant following the consenting of the K3 proposal would lead to a generating station which had a capacity in excess of 50MW. The WKN project did not satisfy that criterion and therefore did not fall within the definition of an NSIP.

4

As part of the preparation of the application for the projects, on 1 st June 2018 the claimant wrote to the defendant to request that the defendant exercise the power under section 35 of the 2008 Act to direct that the WKN facility be treated as a development for which development consent is required, and thereby bring it within decision-making processes of the 2008 Act. The section 35 application explained that the WKN proposal was “an entirely stand-alone facility, and not an extension to [the Kemsley plant]”. Given the close physical proximity between the K3 and the WKN proposals, on the basis that they were proposed to be developed on adjacent sites, the application emphasised the added efficiency to the decision-making process which would arise were they to be considered as part of the same application for a Development Consent Order (“DCO”) for both proposals.

5

On 27 th June 2018 the defendant granted the section 35 application. In doing so the defendant noted that the development did not currently fall within the definition of an NSIP and therefore it was appropriate to consider use of the power in section 35 of the Act. The defendant was satisfied, on the basis that the WKN proposal sat on the same site as two significant applications, including the K3 proposed application, that cumulatively the developments located on the same site could “comprise a significant facility of national sustainable energy supply”. The defendant directed that an application for the form of development described in the request of 1 st June 2018 was to be treated as a proposed application for which a DCO was required, and that any consultation carried out prior to the date of the section 35 direction was to be treated as complying with the consultation requirements under the 2008 Act notwithstanding that it had been carried out prior to the date of the direction.

6

On 11 th September 2019 the claimant applied for a DCO in relation to both the K3 and the WKN projects. Although, as noted above, the projects were separate and distinct, in the application they were combined, as anticipated by the section 35 application, within an application for a single DCO. Pursuant to section 55 of the 2008 Act the application was accepted for examination on 8 th October 2019. The examination began on 19 th February 2020 and concluded on 19 th August 2020.

7

The examination proceeded in the form of a series of written exchanges provided in accordance with a structure of eight Deadlines for the submission of material. One of the issues which the examination addressed was the question of whether or not there was sufficient waste arising in order to support the proposed facilities whilst complying with principles of the waste hierarchy and the proximity principle. Participants in the examination included Kent County Council (“KCC”) who are the waste planning authority for the area within which the proposals lie. KCC, assisted by BPP Consulting, who had provided them with advice in relation to the Early Partial Review of the Kent Minerals and Waste Local Plan (“the EPR”), presented submissions to the examination at the stage of Deadline 1 contending that there was no robust evidence to justify the need for the facilities in terms of the availability of appropriate waste to support the proposed energy from waste capacity. KCC contended that whilst the claimant's evidence in relation to additional suitable waste capacity produced in support of the application stated it lay within a range of 495,540 tonnes per annum and 840,463 tonnes per annum, BPP Consulting had undertaken a sensitivity analysis using the Environment Agency's WDI 2018 data and the claimant's methodology and found that the range actually fell between -760,390 tonnes per annum and -373,473 tonnes per annum.

8

At Deadline 3 of the examination, the claimant submitted evidence disputing the validity of the sensitivity analysis produced by KCC and BPP Consulting. The claimant indicated that it had tried to replicate the BPP Consulting figures but was unable to do so. The claimant produced its own table which reproduced the two original analyses, firstly, produced by the claimant in support of the application and, secondly, produced by KCC at Deadline 1, and then added a further calculation based on the WDI 2018 data that showed a remaining level of need ranging between 306,554 tonnes per annum and 680,032 tonnes per annum. Whilst this showed a reduction over the original calculation supporting the application, the claimant contended that there was still a substantial need for residual waste treatment capacity even after both of the proposals had been consented.

9

Immediately after Deadline 3, on 23 rd April 2020, the Inspector's report on the examination of the EPR was published. As the name of the document implied, the EPR contained a number of proposals to modify the Kent Minerals and Waste Local Plan adopted in 2016, including KCC's position that it was no longer proposed to produce a Waste Sites Plan following a reassessment of the need for waste facilities over the plan period. The evidence base for the EPR included a further assessment of need. The EPR Inspector set out the essence of that exercise and the conclusions arising in the following terms:

“20. The Capacity Requirement for the Management of Residual Non-Hazardous waste (CRRNH) has assessed the need for provision for residual non-hazardous waste arising in Kent, including Local Authority Collected Waste (LACW) and Commercial and Industrial (C&I) waste, as well as some waste originating from London. The calculation of need takes into account revised recycling rates which are based on government guidance and the actual rates achieved. The forecast requirement is based on continuing reductions in landfill.

21. The CRNNH considers the capacities of existing consented facilities and the extent to which they would satisfy identified need. A permitted facility at Barge Way has not been built. Irrespective of whether there is any uncertainty as to whether that facility will be provided, the strategy for waste management capacity does not depend on its provision. Waste arisings are forecast for intervals of 5 years up to the end of the Plan period in 2030/31. The proposed diversion of LACW and C&I waste from landfill is greater than that in the KMWLP. The proportions of those waste streams that are to be subject to other recovery instead of recycling/composting are greater in the EPR than in the KMWLP, taking into account the re-assessed recycling rates.

22. Since the adoption of the KMWLP, a significant new waste recovery facility has been built at Kemsley and is being commissioned. This provides capacity of 525,000 tonnes per annum (tpa). Policy CSW7 of the KMWLP identifies a recovery requirement of 562,500...

To continue reading

Request your trial

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT