Jeffrey Cartwright v Venduct Engineering Ltd

JurisdictionEngland & Wales
JudgeLord Justice Coulson,Lady Justice Arden,Lord Justice Henderson
Judgment Date17 July 2018
Neutral Citation[2018] EWCA Civ 1654
CourtCourt of Appeal (Civil Division)
Docket NumberCase No: A2/2018/0185
Date17 July 2018
Between:
Jeffrey Cartwright
Claimant / Respondent
and
Venduct Engineering Limited
Defendant / Appellant

[2018] EWCA Civ 1654

Before:

Lady Justice Arden

Lord Justice Henderson

and

Lord Justice Coulson

Case No: A2/2018/0185

IN THE COURT OF APPEAL (CIVIL DIVISION)

ON APPEAL FROM Leicester County Court

Regional Costs Judge Hale

B37YP015

Royal Courts of Justice

Strand, London, WC2A 2LL

Mr Benjamin Williams QC (instructed by BC Legal) for the Defendant/Appellant

Mr Andrew Hogan (instructed by MRH Solicitors) for the Claimant/Respondent

Hearing date: Thursday 28th June 2018

Lord Justice Coulson

Introduction

1

This ‘leap-frog’ appeal raises two issues arising out of the rules concerned with Qualified One Way Costs Shifting (“QOWCS”). They are:

i) Issue 1: Whether defendant B can enforce an order for costs out of sums payable to the claimant by way of damages and interest by defendant A;

ii) Issue 2: If the answer to Issue 1 is Yes, whether enforcement is possible if those sums are payable to the claimant by way of a Tomlin order, rather than a direct order of the court for damages and interest.

2

Although counsel identified a third issue, to the effect that, even if the answer to both Issues 1 and 2 is Yes, defendant B would not have been entitled to enforce the order against the claimant on the facts of this case (because the sum to be paid was a global figure for damages, interest and costs), I am firmly of the view that this is not a separate dispute, but arises as part of any consideration of Issue 2.

3

The CPR and the Authorities

4

The QOWCS regime is set out in four short rules ( r.44.13 r.44.16) in Section II of Part 44 of the CPR. Rule 44.13 makes plain that the regime applies to, amongst others, “proceedings which include a claim for damages for personal injuries”. It is common ground that it applied in this case.

5

Rules 44.14–44.15 provide as follows:

Effect of qualified one-way costs shifting

44.14

(1) Subject to rules 44.15 and 44.16, orders for costs made against a claimant may be enforced without the permission of the court but only to the extent that the aggregate amount in money terms of such orders does not exceed the aggregate amount in money terms of any orders for damages and interest made in favour of the claimant.

(2) Orders for costs made against a claimant may only be enforced after the proceedings have been concluded and the costs have been assessed or agreed.

(3) An order for costs which is enforced only to the extent permitted by paragraph (1) shall not be treated as an unsatisfied or outstanding judgment for the purposes of any court record.

Exceptions to qualified one-way costs shifting where permission not required

44.15

(1) Orders for costs made against the claimant may be enforced to the full extent of such orders without the permission of the court where the proceedings have been struck out on the grounds that –

(a) the claimant has disclosed no reasonable grounds for bringing the proceedings;

(b) the proceedings are an abuse of the court's process; or

(c) the conduct of –

(i) the claimant; or

(ii) a person acting on the claimant's behalf and with the claimant's knowledge of such conduct,

is likely to obstruct the just disposal of the proceedings.”

6

Rule 44.16 goes on to address other exceptions to QOWCS. It is common ground that these do not apply here. This case is solely concerned with the proper interpretation of r.44.14.

7

The significance of the QOWCS regime was addressed by this court in Wagenaar v Weekend Travel Limited [2014] EWCA Civ 1105; [2015] 1 WLR 1968, in which Vos LJ said:

“26. It is worth mentioning also that, as was pointed out in argument, the introduction of the QOCS regime is part of a wholesale reform of the funding of personal injury litigation. It is just one of a raft of interconnected changes. If QOCS were to be struck down, there would need to be a complete rethink of the entire Jackson reform programme as it affects personal injury litigation. It will be noted also that the changes in respect of the recoverability of success fees under conditional fee agreements and of ATE premiums were effected by primary legislation as they needed to be: see sections 44 and 46 of the Legal Aid, Sentencing and Punishment of Offenders Act 2012, which amended the CLSA 1990.

36. I should start by referring briefly to the Jackson Report, pursuant to which QOCS was introduced. I shall not repeat here the careful discussion in Chapters 9 and 19 of the Jackson Report. Suffice it to say that the rationale for QOCS that Sir Rupert Jackson expressed in those sections came through loud and clear. It was that QOCS was a way of protecting those who had suffered injuries from the risk of facing adverse costs orders obtained by insured or self-insured parties or well-funded defendants. It was, Sir Rupert thought, far preferable to the previous regime of recoverable success fees under CFAs and recoverable ATE premiums. There is nothing in the Jackson Report that supports the idea that QOCS might apply to the costs of disputes between those liable to the injured parties as to how those personal injury damages should be funded amongst themselves.”

8

Although in some ways the QOWCS regime reflects the pre-1999 Legal Aid scheme, it represents a major departure from the traditional principle that costs follow the event and that, save in unusual circumstances, the losing party pays the winning party's costs. The QOWCS regime provides that, subject to limited exceptions, a claimant in a personal injury claim can commence proceedings knowing that, if he or she is unsuccessful, he or she will not be obliged to pay the successful defendant's costs.

9

The only general exception to that is r.44.14(1), which permits a defendant with a costs order in its favour to recover the amount of that order, but only to the extent that the claimant will recover damages and interest for that amount or more. Thus, the amount that is payable to the claimant by way of damages and interest is a cap on the amount which a defendant can seek by way of enforcement of any costs order(s) in its favour. If the claimant is unsuccessful, then the defendant will recover nothing, despite those costs orders.

10

It should be emphasised that one of the principal purposes of QOWCS is to provide some assistance to claimants with personal injury claims. It is not to penalise their prospective defendants. So I disagree with paragraph 22 of Mr Hogan's skeleton argument, that a central feature of the regime is that defendants “would have to stand their own costs in unsuccessful claims”. That might be a common outcome of the QOWCS regime, but it is not its principal purpose or intent. If a defendant can bring itself within r.44.14(1), then it can recover its costs.

The Factual Background

11

On 19 November 2015, the claimant issued proceedings against six named defendants for noise induced hearing loss (“NIHL”). The third defendant, Venduct Engineering Limited (“Venduct”) accepted that it was responsible for any liability that was established on the part of D1 and D2. The claims against those defendants were therefore discontinued by consent.

12

The claim was transferred to Leicester County Court. It was allocated to the fast track and directions were given for the early hearing of a trial of the limitation issue. That was fixed for 18 January 2017.

13

On 12 December 2016, the claimant compromised its claim against D4 – D6. That compromise was in the form of a Tomlin order. It ordered that all further proceedings in respect of the claims against D4—D6 were stayed, except for the purposes of carrying out the agreed terms of settlement, which were set out in a separate schedule. The schedule provided that:

“The claimant do accept the sum of £20,000 in full and final settlement of his cause of action against the fourth, fifth and sixth defendant, inclusive of general damages, special damages, costs of the action, interest, and CRU.”

14

At about the same time, on 7 December 2016, the claimant served a notice of discontinuance in respect of the claim against Venduct. CPR 38.6(1) provides that, unless the court orders otherwise, “a claimant who discontinues is liable for the costs which the defendants against whom the claimant discontinues incurred on or before the date on which notice of discontinuance was served on the defendant”. Accordingly, Venduct's solicitors asserted that they had the right to recover the costs (approximately £8,000) which they had incurred as a result of the claimant's claim. They maintained that this could be paid out of the £20,000 paid by D4 — D6 pursuant to the terms of the Tomlin order.

15

In response, the claimant said that it had the protection of the QOWCS regime, such that one defendant could not take advantage of sums payable by another defendant to the claimant. In addition, the claimant alleged that, since the sums from D4 – D6 were paid by way of a Tomlin order, which reflected a contractual agreement between the parties, there had been no “order for damages and interest made in favour of the claimant”, so Venduct could not rely on r.44.14 in any event.

The Judgment

16

These were therefore the two issues that came before Regional Costs Judge Hale in the Nottingham County Court. In an impressive reserved judgment dated 6 December 2017, the Costs Judge dealt with the Tomlin order issue first. He decided that issue against Venduct, concluding that the claimant's entitlement to damages arose, not by reason of an order of the court for damages, but by reason of an agreement with D4 – D6. This analysis was based on the decisions of Ramsey J in Community Care North East v Durham County Council [2012] 1 WLR 338 and the Court of Appeal in Watson v Sadiq [2013] EWCA Civ 822. As the Costs Judge noted, those cases were authority for the general proposition that,...

To continue reading

Request your trial
10 cases
  • The Scout Association v Bolt Burdon Kemp
    • United Kingdom
    • King's Bench Division
    • 17 October 2023
    ...which the Defendant could enforce an order for costs without the permission of the court (see Cartwright v Venduct Engineering Limited [2018] 1 WLR 6137, at paragraph 44). The effect of the decision in Ho (handed down on 6 October 2021) is that the Defendant is also unable to recover its c......
  • Mrs Siu Lai Ho v Miss Seyi Adelekun
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 9 April 2020
    ...QOCS rules are not intended to affect the liability of a claimant to pay her own solicitors. In Cartwright v Venduct Engineering Ltd [2018] EWCA Civ 1654, [2018] 1 WLR 6137 Coulson LJ described the purpose and effect of the QOCS regime in these terms: “7. Although in some ways the QOWCS r......
  • Mrs Siu Lai Ho v Miss Seyi Adelekun
    • United Kingdom
    • Supreme Court
    • 6 October 2021
    ...to a Tomlin order, and therefore no headroom below the cap available under QOCS for the defendant's costs enforcement: see Cartwright v Venduct Engineering Ltd [2018] EWCA Civ 1654; [2018] 1 WLR 6137 (“ Cartwright”). The third type is where the aggregate of the costs that the claimant is ......
  • The Commissioner of Police of the Metropolis v Andrea Brown
    • United Kingdom
    • Queen's Bench Division
    • 31 July 2018
    ...37 (After I had circulated this judgment in draft to the parties, Ms Brown's solicitors sent me a copy of the transcript in Cartwright v Venduct Engineering Ltd [2018] EWCA Civ 1654, handed down on 17 July 2018. I am grateful for sight of that judgment which concerns the operation of CPR 44......
  • Request a trial to view additional results
5 firm's commentaries
  • QOCS Changes In April 2023: The Practical And Tactical Implications For Claimants And Their Solicitors
    • United Kingdom
    • Mondaq UK
    • 27 March 2023
    ...along to clear up the anomaly resulting from the decisions in the Appellate courts, this time in Cartwright v Venduct Engineering Ltd [2018] EWCA Civ 1654; [2018] 1 WLR 6137 and Ho v Adelekun [2021] UKSC 43; [2021] 1 WLR As all PI litigation lawyers know, Cartright precluded enforcement in ......
  • What Does 2023 Hold For PI Lawyers?
    • United Kingdom
    • Mondaq UK
    • 3 January 2023
    ...changes to CPR 44 (see the minutes of the October 2022 meeting) to plug the hole identified in Cartwright v Venduct Engineering [2018] EWCA Civ 1654 that settlements, including acceptance of Part 36 offers, are not orders of the court which allow a defendant to enforce a costs order against......
  • Set Off To Get Lift Off: Changes To The QOCS Regime
    • United Kingdom
    • Mondaq UK
    • 30 May 2022
    ...to be set off against both costs and damages To resolve the issue caused by the Court of Appeal in Cartwright v Venduct Engineering [2018] EWCA Civ 1654 where the Court of Appeal stated that acceptance of a 36 offer does not create an enforceable order for the purposes of QOCS. The decision......
  • Court Of Appeal Rules On Applicability Of QOCS Where Settlement Is Reached Via Tomlin Order
    • United Kingdom
    • Mondaq UK
    • 26 July 2018
    ...v Venduct Engineering Ltd [2018] EWCA Civ 1654 The Court of Appeal has upheld a first instance decision confirming that a successful defendant can recover costs from damages payable to a claimant by an unsuccessful co-defendant in the same However, such a recovery is limited to where an ord......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT