Mott Macdonald Ltd v London & Regional Properties Ltd

JurisdictionEngland & Wales
JudgeHH Judge Thornton QC,Judge Thornton QC
Judgment Date23 May 2007
Neutral Citation[2007] EWHC 1055 (TCC)
Docket NumberCase No: HT-07–29
CourtQueen's Bench Division (Technology and Construction Court)
Date23 May 2007

[2007] EWHC 1055 (TCC)

IN THE HIGH COURT OF JUSTICE

Technology and Construction Court

St Dunstan's House,

131 – 137 Fetter Lane,

London,

EC4A 1HD

Before

Hh Judge Thornton QC

Case No: HT-07–29

Between
Mott Macdonald Limited
Claimant
and
London & Regional Properties Limited
Defendant

Mr Alexander Nissen QC (instructed by Shadbolt & Co LLP, Chatham Court, Lesbourne Road, Reigate, Surrey, RH2 7LD, DX 30402, Reigate-1, mail@shadboltlaw.com, Ref: MRD/SC/KET/2716.1/432327.1) for the claimant.

Mr Hamish Lal, Solicitor Advocate (Dundas & Wilson LLP, Northwest Wing, Bush House, Aldwych, London, WC2B 4EZ, DX 127 LDE, Hamish.Lal@dundas-wilson.com Ref: HL/EB.LON016.0243) for the defendant.

Hearing dates: 1 March 2007 followed by written submissions

Judge Thornton QC

Judge Thornton QC

1
1

The claimant, Mott MacDonald Ltd (“MM”) is a specialist engineering multi-disciplinary consultancy providing services to the construction industry and the defendant, London & Regional Properties Ltd (“LRP”) is a property developer. LRP is developing a business park at Park Royal, London known as First Central Park and MM undertook professional services as Highways and Transport Engineers in relation to the planning and engineering design for the phase 2 infrastructure works for this development, particularly in relation to the necessary planning application and the subsequent detailed engineering design work for various roadworks and bridges, necessary negotiations and liaison with interested parties and site supervision. These services were carried out between December 1997 and February 2006. MM continued thereafter to carry out professional services in relation to this development.

2

A dispute arose as to the non-payment of invoiced fees that had been earned in the period January 2003 until February 2006. The total sum claimed, exclusive of VAT, was £62,767.52. LRP had declined to pay these sums due to disagreements as to whether MM was entitled to claim fees on the grounds that the formal agreement providing for MM's consultancy services on this project had not been finalised and executed and because, at the time that the dispute crystallised into a formal adjudication claim, that it might have a set off. However, since no proper withholding notices had been served, the dispute related entirely to whether MM had a contractual entitlement to claim fees and, if so, on what basis.

3

MM served an adjudication notice dated 25 October 2006 and on 26 October 2006 applied to the RICS to appoint an adjudicator under the construction contract it was contending governed the parties' contractual relationship or under the Scheme for Construction Contracts (England and Wales) Regulations 1998 if there was no contractual adjudication clause in existence. An adjudicator was appointed by the RICS on 31 October 2006. LRP raised a jurisdictional challenge which the adjudicator was not prepared to accede to and, following an agreed extension of the time by which he had to reach his decision until 13 December 2006, the adjudicator issued to the parties a decision dated 13 December 2006 which MM and LRP received by post on 14 December 2006. That decision provided for the payment in full of MM's claim within 7 days of the date of the decision but it declined to direct payment of MM's claims for contractual interest. The decision directed that 90% of the adjudicator's fees, totalling £8,803.69 should be paid by LRP and the balance by MM. Since MM had already paid the entire sum invoiced by the adjudicator to him, the decision directed that LRP should reimburse MM that sum. LRP has declined to pay MM the directed sum or the share of the adjudicator's fees it was directed to pay and, in a claim form issued on 30 January 2007, MM now seeks summary judgment of these sums plus interest by way of enforcement of the decision.

4

The basis on which enforcement is resisted was only finally and clearly established in the detailed written submissions that I directed should be served following the brief one hour oral hearing. This procedure was adopted because the claim is for a relatively small sum but the enforcement issues were complex and only one hour had been fixed for the hearing. This time estimate was inadequate and the hearing would have had to have been adjourned part heard to a different day had written submissions not been directed as an alternative. The parties' advocates are to be commended for the quality and clarity of the written and oral submissions that they provided before, during and following this brief hearing.

2

Issues

5

The challenge to the enforcement application is in two parts, being in part a jurisdictional challenge relating to the adjudicator's alleged lack of jurisdiction when appointed and, in part, a procedural challenge relating to the timing of the delivery of his decision to the parties.

6

The jurisdictional issues are, on analysis, multi-layered. The first two issues were whether there was a contract at all (issue 1) and, if there was, whether it was it a construction contract (issue 2). The principle issue, raised by LRP, was, assuming that there was a construction contract, whether it was in writing as defined by section 107(2) of the Housing Grants Construction and Regeneration Act (“ HGCRA”) so as to make Part II of the HGCRA applicable (issue 3). If section 107(2) was not applicable, an issue arose as to whether section 107(5) of the HGCRA was applicable (issue 4). Finally, if section 107 did not provide the necessary statutory foundation for the adjudication, MM contended that LRP had nonetheless voluntarily submitted to the jurisdiction of the adjudicator (issue 5) and that the decision of the adjudicator that he had jurisdiction is now unreviewable since the relevant findings were made by the adjudicator within his jurisdiction (issue 6).

7

The procedural issues can be sub-divided into four sub-issues. Firstly, was the adjudicator entitled to impose a pre-condition on the delivery of his decision to the parties that his fees should first be paid by the referring party (issue 7)? Secondly, when did the adjudicator reach his decision (issue 8)? Thirdly, was a copy of the decision delivered to each of the parties as soon as possible after it had been reached (issue 9)? Fourthly, what is the effect on the validity and enforceability of the decision of the answers given to issues (7)—(9) (issue 10)?

3

Jurisdictional Challenges

3.1

Factual Background

8

The first contact between LRP and MM occurred in November 1997 when LRP invited MM to submit a proposal for its appointment to provide professional services in relation to the new business park being planned at Park Royal, London. The appointment was to be in connection with the intended planning application for the infrastructure works which would involve a significant highways and traffic element. MM's proposal was submitted in a letter dated 3 December 1997. No formal contract resulted but professional services were provided and invoiced by MM and paid for by LRP. Whatever the precise contractual relationship was between the parties during this phase of the design work, that contract came to an end once MM's planning permission services were completed.

9

By a letter dated 4 November 1998, LRP's consultants sent MM a request to provide a proposal for engineering consultancy services in respect of the detailed design and supervision stages of the project, being Phase 2 of the infrastructure works. MM submitted a detailed proposal which split the assumed work into three elements, being the design of the infrastructure roadworks and bridges, the negotiations with the various interested parties in relation to planning, highways and railways agreements and site supervision. The letter made it clear that it would be necessary to define elements of work and the scope of MM's services more precisely at a later stage. It was not clear at that stage whether MM would be engaged by LRP or by the contractor, when appointed, to provide similar design services under a design and build contract arrangement. Different forms of contract were proposed depending on which contracting arrangement was ultimately settled upon.

10

Planning for this phase of the pre-construction work developed somewhat slowly. Thus, on 6 April 1999, MM sent LRP's consultants a document entitled Scope of Services for Detailed Design of The Highways Works. On 14 May 1999, LRP's former solicitors sent MM a proposed appointment document. No schedule of services was appended since these remained to be compiled and agreed. The document was stated to be applicable only to the first of the three phases of the works, being the infrastructure roadworks but as also being the likely document for any other phase undertaken by MM.

11

MM sent LRP's consultants a preliminary fee profile for this proposed appointment on 6 July 1999. The letter stated that a full fee profile could be developed once the scope of works had been better defined and it would also need reviewing once other changes to structural elements had been finalised. A further fee profile was produced dated 6 August 1999 which was sent to the consultants with a letter dated 20 September 1999.

12

On 28 September 1999, the consultants sent MM a letter entitled “Letter of Intent: Highways and Transport Engineers”. This was clearly a reference to the proposed engagement to provide engineering consultancy services that had been sent to MM on 4 November 1998. The letter stated that it was the confirmation of LRP's instruction for MM to commence and proceed with the Works pending final agreement and execution of the Contract. The Works were defined as “the Highways and Engineers services for Phase 2 of the infrastructure works” and the scope of the works was stated to be identified in the bid letter dated 4 November 1999 and MM's proposal dated 26 November 1999 and its two...

To continue reading

Request your trial
4 cases
  • Glendalough Associated SA v Harris Calnan Construction Company Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 21 October 2013
    ...was most in point is the decision of His Honour Judge Thornton QC, a judge who is very experienced in this field, in Mott MacDonald v London and Regional Properties Ltd [2007] EWHC 1055 (TCC). He said that the subsection required the party to have alleged that there was an agreement otherwi......
  • Lee v Chartered Properties (Building) Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 25 June 2010
    ...Barnes & Elliott.” I respectfully agree with these observations. 30 HHJ Thornton QC considered these cases again in Mott MacDonald Ltd v London & Regional Properties Ltd [2007] EWHC 1055 (TCC) in which the decision dated 13 December 2006 was sent by post and received by the parties on 14 De......
  • Harris Calnan Construction Company Ltd v Ridgewood Kensington Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 15 November 2007
    ...Electrical Services Ltd. -v—Inviron Ltd. [2007] EWHC 46 (TCC), and the decision of His Honour Judge Thornton Q.C. in Mott McDonald Ltd. -v—London & Regional Properties Ltd. [2007] EWHC 1055 (TCC), in which the particular letters of intent in question were ruled not to be contracts where all......
  • Chip Hup Hup Kee Construction Pte Ltd v Ssangyong Engineering & Construction Co Ltd
    • Singapore
    • High Court (Singapore)
    • 26 November 2009
    ...signature for the determination to be valid. 46 In the English case of Mott MacDonald Limited v London & Regional Properties Limited [2007] EWHC 1055 (TCC) in the context of the 1996 UK Act and 1998 UK Scheme, one procedural challenge to the decision of the adjudicator at [80] was that the ......
5 firm's commentaries
  • Construction, Property & Real Estate (Case Law Review, Issue 7, 2007)
    • United Kingdom
    • Mondaq United Kingdom
    • 1 November 2007
    ...fall within the s.105(2)(c) definition of plant and equipment. Jessica Stephens Mott McDonald Ltd v London & Regional Properties Ltd [2007] CILL 2481 A letter of intent between the claimant consultant and the defendant client was held not to be an agreement in writing for the purposes o......
  • Timelines In Adjudication And Adjudicator's Powers
    • United Kingdom
    • Mondaq UK
    • 9 October 2023
    ...ability to release that decision. This was discussed further in the case of Mott Macdonald Ltd v London & Regional Properties Ltd [2007] EWHC 1055 (TCC) whereby this very scenario occurred. It was established that the Adjudicator could not impose a lien on his decision pending the payment o......
  • Paying An Adjudicator To Release His Decision Imperils It
    • United Kingdom
    • Mondaq United Kingdom
    • 5 June 2007
    ...within 28 days of the referral or the extended period). Reference: Mott MacDonald Limited v London & Regional Properties Limited [2007] EWHC 1055 (TCC). This article was written for Law-Now, CMS Cameron McKenna's free online information service. To register for Law-Now, please go to Law......
  • Another Day, Another Adjudication Notice - Are There Any Get Out Clauses?
    • United Kingdom
    • Mondaq UK
    • 4 October 2022
    ...which would breach the obligations of the adjudicator under The Scheme: Mott Macdonald Ltd v London & Regional Properties Ltd [2007] EWHC 1055 (TCC) - the court held that the adjudicator refusing to issue his decision until the referring party had paid his fees was a breach of the adjudicat......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT