Arcadis Consulting (UK) Ltd (formerly called Hyder Consulting (UK) Ltd) v AMEC (BCS) Ltd (formerly called CV Buchan Ltd)

JurisdictionEngland & Wales
JudgeDame Elizabeth Gloster,Lord Justice Underhill,Lord Justice Holroyde
Judgment Date10 October 2018
Neutral Citation[2018] EWCA Civ 2222
CourtCourt of Appeal (Civil Division)
Docket NumberCase No: A1/2016/4266
Date10 October 2018

[2018] EWCA Civ 2222

IN THE COURT OF APPEAL (CIVIL DIVISION)

ON APPEAL FROM THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

TECHNOLOGY AND CONSTRUCTION COURT

The Hon. Mr Justice Coulson

[2016] EWHC 2509 (TCC)

Royal Courts of Justice

Strand, London, WC2A 2LL

Before:

Lord Justice Underhill

(Vice-President of the Court of Appeal (Civil Division)

Lord Justice Holroyde

and

Dame Elizabeth Gloster

Case No: A1/2016/4266

Between:
Arcadis Consulting (UK) Limited (formerly called Hyder Consulting (UK) Limited)
Appellant
and
AMEC (BCS) Limited (formerly called CV Buchan Limited)
Respondent

Mr Marcus Taverner QC and Mr Gideon Scott Holland (instructed by Herbert Smith Freehills LLP) for the Appellant

Mr Simon Hughes QC and Mr Calum Lamont (instructed by DAC Beachcroft LLP) for the Respondent

Hearing date: 1 May 2018

Judgment Approved

Dame Elizabeth Gloster

Introduction

1

This is an appeal by Arcadis Consulting (UK) Limited (“Hyder” or “the appellant”) against the judgment dated 25 October 2016 (“the judgment”) and the consequential order dated 18 November 2016 of Coulson J (“the judge”) in which the judge found that Hyder and AMEC BCS Limited (“Buchan” or “the respondent”) had agreed a simple contract (“the Contract”) arising out of Buchan's first letter of 6 March 2002 (“the First 6 March Letter”) and Hyder's acceptance of it. The judge further concluded that no set of terms and conditions were incorporated into the Contract.

2

Hyder is a management consultancy and engineering business. On 18 September 2015 Hyder changed its name to Arcadis Consulting (UK) Limited.

3

Buchan is a contractor specialising in the design, manufacture and installation of pre-cast concrete for the civil engineering and construction industries. In or about 2007, Buchan changed its name to AMEC (BCS) Limited.

4

Buchan acted as the specialist concrete sub-contractor on two large projects, referred to in the documents as the Wellcome Building and Castlepoint Car Park. Buchan engaged Hyder to carry out certain design works in connection with those projects in anticipation of a wider agreement between the parties which, in the event, did not materialise.

5

Kier Build Limited (“Kier”) was the main contractor on the Castlepoint Project.

6

It is now alleged that the Castlepoint Car Park is defective and may need to be demolished and rebuilt. Rebuild costs are said to be many tens of millions of pounds but Buchan's claim against Hyder, linked to the former's settlement with Kier, together with its own damages claim, is put at £40 million. Hyder deny liability for the defects.

7

The substantive hearing took place before Coulson J from 10 October 2016 to 12 October 2016.

8

The central question on this appeal is whether the terms and conditions sent from Buchan to Hyder on 8 November 2001 (“the November Terms”) were incorporated by reference into the Contract found by the judge.

Factual Background

9

The judgment of Coulson J sets out a summary of the relevant facts and documents, which I adopt here.

10

In early 2001, Buchan approached Hyder regarding the possibility of making a framework or protocol agreement under which the parties would work together on different construction projects involving pre-cast concrete components.

11

Stewart Tyler was Hyder's Area Director in its Birmingham Office at the relevant time with responsibility for co-ordinating and overseeing new business relationships. He was involved in the negotiations between the parties between about early 2001 and August 2002.

12

There were discussions between the parties which ranged over many months and many topics. Mr Shotliff, Buchan's commercial director, met his opposite number, Mr Tyler, on a number of occasions. One of the points which they discussed was a cap on Hyder's liability “where liability is not covered by insurance” (see Mr Shotliff's notes of his meeting with Mr Tyler dated 28 September 2001). This suggested a link between the cap and insurance which was sometimes clear in the exchanges, and sometimes not. On 8 November 2001, Mr Shotliff emailed Mr Tyler to say:

“Please find attached the updated documents we propose to use for design work. The Terms and Conditions document is merely tidied up as I understand. The Protocol document is intended to be the instrument that creates the Agreement. It will be necessary to agree particular schedules for each contract in addition to these and further minor amendments may still be required. We intend to use the documents for the Wellcome Building works subject to your agreement and we will be providing more details shortly. Accordingly I would be grateful if you could make any comments you may have as soon as possible as we are about to start your works on the above basis on this contract.”

13

The attached documents included:

(a) the Protocol Agreement, which was in the form of an umbrella agreement, which envisaged separate schedules and work instructions for each specific contract, but which nonetheless envisaged that each separate contract would be carried out pursuant to the same general terms and conditions; clause 2.1 of the Protocol Agreement envisaged that all these documents would then form a suite of contract documents, with a stated order of precedence; clause 5.3 required a £5 million level of PI insurance cover;

(b) the schedules to the Protocol Agreement, which included a template work instruction and a work instruction acceptance;

(c) the detailed terms and conditions, which would themselves form a schedule to the Protocol Agreement; Condition 2A was entitled ‘Limit of Liability’ and stated:

“The Consultant's liability for defective work under the Agreement shall be limited to whichever is the lesser of the following:

(a) The reasonable direct costs of repair, renewal and/or reinstatement of any part or part of the Sub-Contract Works to the extent that the Client incurs such costs and/or is or becomes liable either directly or by way of financial contribution for such costs; or

(b) The sum stated in Schedule 1.”;

this was the proposed liability cap in its original form;

(d) clause 7 of the terms and conditions required insurance in the form and to the level set out in Schedule 6 (which was blank in the version sent out on 8 November);

(e) schedule 1, at paragraph M, stated that “the limit, if any, on the Consultant's liability for defects in the design (as referred to in Clause 2A) is…; there was a space in which the relevant figure could then be entered; in the version that was sent, that was, of course, blank;

(f) schedule 2 was to be a detailed description of the services to be performed by Hyder under the specific work instruction; and

(g) schedule 3 dealt with fees.

14

On 9 November 2001, Hyder wrote to Buchan in relation to the Wellcome Centre and said:

“I understand that discussions between David Shotliff and Stewart Tyler on the Design Services Agreement are well advanced. However, it may still take a little time before this Agreement is formally signed. In the meantime I should be grateful if you would confirm that you would underwrite our fees for the design and drawing work and in order that there is a basis for these, propose the following schedule of rates…”

15

On 13 November 2001, Buchan replied acknowledging Hyder's letter of 9 November 2001, anticipating agreement on the Protocol Agreement within two weeks. They instructed Hyder to start work on the design for the Wellcome Centre. They went on:

“Your work done under this instruction is to be on the basis of our instructions from Wates and the conditions and terms detailed in the Protocol Agreement, Design Consultancy Terms and Conditions in your possession at present.

It is our intention to enter these Agreements with yourselves in their present form with such minor amendments as maybe mutually agreed and to award you the Design Works on the Wellcome Building Precast Concrete Package in the sum of £55,000 as previously agreed.

Pending formalisation of these Agreements, we will pay you for work done under this instruction up to a maximum £10,000.

Once the Agreements are executed their terms and conditions shall supersede this letter and shall govern any work done retrospectively.”

16

On 14 November 2001, Buchan wrote to Hyder referring, for the first time, to the Castlepoint Car Park. The letter said:

“We are currently preparing our tender for a precast concrete frame and associated works at the above contract and would be pleased to receive your keenest fixed price quotation for the supply of design services as detailed herein…”

The letter said that the works were to be priced on the basis that the quotation was compliant with the “Proposed Design Agreement”.

17

On 28 November 2001, Hyder replied to Buchan's letter of 14 November 2001, in respect of the Castlepoint Car Park. They offered to provide the required structural design and detailing services for the lump sum of £285,000 plus VAT, although this offer was subject to a number of express conditions including:

“(1) Agreement on the terms and conditions of our appointment for provision of the services

(2) Agreement of commencement date and the design programme

(4) Any variations or additional services required to be charged on a time basis at rates to be agreed…”

18

Mr Tyler was being advised by Mr Brand, another Hyder employee, about the acceptability of the Protocol Agreement, and the terms and conditions, which Buchan had proposed on 8 November 2001. On 19 November 2001, Mr Brand advised Mr Tyler that “you should not be considering entering into a contract with them on the basis of their draft, and Hyder should definitely not be using their draft for a standard for use between the companies.” However, it was not until 12 December 2001 that Mr Tyler wrote to Mr Shotliff to express his opposition to the drafts, and he did so in milder terms than those used by...

To continue reading

Request your trial
2 firm's commentaries
  • Court Of Appeal Finds Interim Contract Incorporated Terms And Conditions Including Limitation Of Liability
    • United Kingdom
    • Mondaq UK
    • 30 January 2019
    ...in fact been incorporated by reference, so that the defendant's liability was limited: Arcadis Consulting (UK) Ltd v AMEC (BCS) Ltd [2018] EWCA Civ 2222. The decision suggests that (whilst there are clearly risks in commencing work without a clear written agreement as to the terms that will......
  • Completing The Contract First: Does It Matter?
    • United Kingdom
    • Mondaq UK
    • 15 November 2019
    ...the party, scope or standard of care. If they had, litigation may have been avoided. Arcadis Consulting (UK) Ltd v AMEC (BCS) Ltd [2018] EWCA Civ 2222 AMEC (Buchan) claimed that Arcadis (Hyder) was responsible for the defective design of a car park and should pay £40m. Hyder denied liabilit......
1 books & journal articles
  • Contract formation
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...Ltd v Laing O’Rourke Midlands Ltd [2008] EWHC 1016 (TCC) at [122]–[123], per Ramsey J; Arcadis Consulting (UK) Ltd v AMEC (BSC) Ltd [2018] EWCa Civ 2222 at [92]–[93], per Dame Elizabeth Gloster. See also Vassallo Constructions Pty Ltd v Andergrove Lakes Pty Ltd [2014] FCa 862 at [43], per D......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT