Vision Homes Ltd v Lancsville Construction Ltd

JurisdictionEngland & Wales
JudgeMR JUSTICE CHRISTOPHER CLARKE
Judgment Date04 August 2009
Neutral Citation[2009] EWHC 2042 (TCC)
Docket NumberCase No: HT-09-278
CourtQueen's Bench Division (Technology and Construction Court)
Date04 August 2009

[2009] EWHC 2042 (TCC)

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

TECHNOLOGY AND CONSTRUCTION COURT

Before: Mr Justice Christopher Clarke

Case No: HT-09-278

Between:
Vision Homes Ltd
Claimant
and
Lancsville Construction Ltd
Defendant

Peter Fraser QC & Simon Crawshaw (instructed by Maxwell Winward LLP) for the Claimant

Martin Bowdery QC & Stuart V Kennedy (instructed by Merriman White Solicitors) for the Defendant

Hearing dates: 20th July 2009

Approved Judgment

I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.

MR JUSTICE CHRISTOPHER CLARKE MR JUSTICE CHRISTOPHER CLARKE

MR JUSTICE CHRISTOPHER CLARKE:

1

Vision Homes Limited (“Vision”), the claimant, is a property developer. It contends that a decision of Mr Tony Bingham in respect of an adjudication is null, void and of no effect because it was made without jurisdiction and because it is vague and ambiguous. There is also a separate action in which Lancsville Construction Ltd (“LCL”), the defendant, seeks to recover the amount of Mr Bingham's fees.

2

In October 2007, Vision entered into a contract (“the contract”) in the form of the JCT Design and Build Contract 2005 Edition (with amendments) with LCL. Under the contract LCL was to construct the structural shell and external envelope (cladding, windows, doors and roofing) to five new blocks of residential apartments being developed by Vision at Paradise Dock, 142 Lea Bridge Road, London E5, together with other landscaping and infrastructure work. The contract sum was £7,975,000. Clause 9.2. of the Conditions provided for disputes under the contract to be referred to adjudication under the Scheme for Construction Contracts (“the Scheme”).

3

Work under the contract began. By July 2008, LCL realised that they were unable to undertake the external envelope works as required by the Contract, because they were unable to provide adequate funding to their proposed sub-contractor for the cladding works. LCL told Vision of the difficulty. Following discussions, in or around July or August 2008 the parties agreed that the external envelope works would be omitted (“de-scoped”) from the Contract, resulting in a 40% reduction in the value of the works. The agreement was preceded by an e-mail of 10th July in which Mr Freeman of Vision said to Mr Sherry of LCL:

“..we are not looking for compensation or to get caught in contractual negotiations…”

4

With regard to the remaining works which stayed with LCL, the parties agreed a revised method of working for Block 5 and other fundamental changes to the way the work was to proceed and be handed over. According to the evidence of Mr Wallace of Kingfisher Associates Ltd, LCL's advisor, the works then proceeded on the basis that LCL would complete the remaining sections of the frame to blocks 2 and 3 and hand them over floor by floor. This contrasted with the original arrangement in which it had been envisaged that LCL would complete the whole frame including envelope works and then hand them over to Vision for internal fit out and completion. By 21 st July LCL notified Vision that blocks 1 and 4 had reached practical completion, which Vision accepted at the time. Block 5 had fallen substantially behind schedule on account of problems with planning permission. It was agreed that the works would be carried out but again on an entirely different basis. LCL would complete the ground floor slab. Vision's employees would then carry out the brick and block work on the slab and then LCL would return and cast the next floor on the metal sheeting provided and installed by Vision and so on.

5

The effect of the changes (according to LCL) is summarised at pages and 6 of Mr Bingham's decision as follows:-

“LCL says: This Agreement substantially altered and drastically reduced the scope of Works. It altered the nature of the possession of the site and/or sections or parts thereafter and the issue of Practical Completion, LADS and the issuing of non-completion notices. The 'Notice of Adjudication' then particularises the effects of LCL position and continues: This project has an original contract value of £7.9 million. The contract indicates the amended document JCT 2005 Design and Build set of rules signed under seal and dated 05 October 2007. The subsequent July 2008 Agreement reduced the contract value by approximately £3 million down to £4.9 million. One of the effects of this agreement is an intention not to deduct Liquidated & Ascertained Damages. Further, or alternatively partial possession was taken with the effect of proportionate reduction of LADS. Further, the Agreement fundamentally altered the contractual matrix. Vision became in full control of the site, it was doing the majority of the Works and had CDM implications. Further, various practical completion status arose. The right to insist on performance of the contract in respect of time was lost and became at large. LCL effectively became a Vision subcontractor. Alternatively says LCL the Agreement had the effect of LCL taking partial possession of the whole site. Alternatively the effect of the Agreement is that it provides “yet another series of dates”.

6

According to LCL by October 2008, the remaining contract works were substantially complete, although no Certificates of Practical Completion or Sectional Completion were issued. However, on 21 st and 28 th November 2008, Vision issued Non-Completion Certificates for the works. On 28 th November LCL submitted to Vision a draft final account. On 26 th March 2009, Vision purported to determine LCL's employment under the Contract.

Adjudications Nos 1 and 2

7

In April 2009, LCL commenced an Adjudication (“Adjudication No. 1”) .in relation to whether the determination of the contract was unlawful, but this was withdrawn before a decision was made and the adjudicator, Mr Lorne Alway of Always Associates, who had been appointed by the RICS, stood down. LCL commenced a second adjudication (“Adjudication No. 2”), with Mr Alway as adjudicator, relating to the non-payment of part of an interim valuation. Vision paid the sum in question and Mr Alway stood down.

8

By a letter dated 1 st May 2009 Vision claimed against LCL £509,254 in Liquidated Damages for alleged late completion in accordance with clause 2.29 of the contract. LCL denied liability on the grounds that the contract dates for completion had been superseded by the agreement reached between the parties in July and August 2008 when the cladding was omitted. There was, therefore, a dispute over whether Vision was entitled to payment under the contract of Liquidated and Ascertained Damages (“LADs”) and what contractual Completion Dates (if any) still applied.

14

th May 2009

Adjudication No 3: LCL's first Notice of Intention to Refer

9

At 0622 on 14 th May Mr Wallace on behalf of LCL faxed to Maxwell Winward on behalf of Vision a letter inviting them to agree one of three candidates to act as Adjudicator and enclosing a Notice of Intention to Refer a Dispute. The Notice included the following:

“6. It is Lancsville's intention to try to agree a nomination for adjudicator and if not apply to the President of the RICS in accordance with the provisions of the Contract for the appointment of an adjudicator for the resolution of the dispute or difference, the terms of which are set out below.

……

The Dispute

8. The dispute or difference between the parties arises out of or in connection with the aforesaid written construction contract in respect of the Works at Paradise Dock, Lea Bridge Rd, London.

9. The Employer has in breach of contract decided to levy LADs in respect of purported late completion. The Adjudicator is requested to investigate all the issue of the agreement and/or the change to the Employer's Requirements and the Change instruction issued by Vision Homes whereby LCL's scope of work was substantially altered and drastically reduced. This agreement then altered the nature of the possession of the site and/or sections or parts thereafter and the whole issue of practical completion, LADs, time and the issuing of non-completion notices. However the Adjudicator is not given jurisdiction to investigate and make any decision as to Lancsville's application for an extension of time.”

LCL included in this notice a “Statement of Relief” sought which read as follows:

“Declarations that:

A: In respect of blocks 1 to 5 Vision Homes amended the Employer's Requirements, by agreement with LCL, and removed from their scope of works the obligations to complete the external envelope including cladding, windows and doors or such other elements as the Adjudicator in his discretion shall decide.

B: The Employer's Requirements were fundamentally changed in respect of Block 5 whereby Vision Homes and LCL carried out the construction Work jointly.

C: Vision Homes issued a Change instruction under clause 3.9 of the Contract to alter the Employer's Requirements.

D: Due to Vision Homes changing the Employer's Requirements and then undertaking either by themselves or through sub contractors all the External envelope work then, for the purposes of possession and/or Practical completion the situation was:

Practical completion of blocks 1 and 4 took place on a date not later than the 21st July 2008.

Phased partial possession by Vision Homes took place under clause 2.30 of the Contract of blocks 2, 3 and 5 in accordance with Mr Naude's letter of the 4th August 2008 reference AD/cc/2410/2 save for the stairwells of blocks 2 and 3.

Practical completion of block 2 took place on a date not later than 27th February 2009 and block 3 on a date not later than 6th March 2009. Block 5 was practically complete on a date not later than 27th March 2009.

Partial possession of...

To continue reading

Request your trial
4 cases
  • Ecovision Systems Ltd v Vinci Construction UK Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 11 March 2015
    ...QC in IDE Contracting Ltd v R.G. Carter Cambridge Ltd [2004] EWHC 36 (TCC) at paras. 9–11 and Christopher Clarke J in Vision Homes Ltd v Lancsville Construction Ltd [2009] EWHC 2042 (TCC) for the proposition that a failure to observe strictly the procedure in the Scheme or in the contractua......
  • Lanes Group Plc v Galliford Try Infrastructure Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 6 July 2011
    ...Judge's reasoning. But if this observation was obiter I nonetheless agree with it. 29 The decision of Christopher Clarke J in Vision Homes v Lancsville Construction [2009] EWHC 2042 is also supportive of this view. One aspect of that case was that both parties had started competing adjudica......
  • Stellite Construction Ltd v Vascroft Contractors Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 14 April 2016
    ...which the reference has been made: see McAlpine PPS Pipeline Systems v Transco [2004] BLR 352 (at paragraphs 145 and 146) and Vision Homes v Lancsville Construction [2009] BLR 525 (at paragraph 61). The adjudicator's jurisdiction includes any defence to the claim advanced in the Notice of A......
  • Liverpool City Council v Vital Infrastructure Asset Management (Viam) Ltd ((in Administration))
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 24 May 2022
    ...without delay or difficulty. I accept the general principle, as illustrated by the decision of Christopher Clarke J in Vision Homes Ltd v Lanscville Construction Ltd [2009] EWHC 2042 (TCC), that an adjudicator will lack jurisdiction where the nomination had been sought prior to service of ......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT