Glory Wealth Shipping PTE Ltd v Korea Line Corporation (The "Wren")

JurisdictionEngland & Wales
JudgeMr Justice Blair
Judgment Date14 July 2011
Neutral Citation[2011] EWHC 1819 (Comm)
Docket NumberCase No: 2010 FOLIO 1375
CourtQueen's Bench Division (Commercial Court)
Date14 July 2011

[2011] EWHC 1819 (Comm)

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

COMMERCIAL COURT

Royal Courts of Justice

Strand, London, WC2A 2LL

Before:

Mr Justice Blair

Case No: 2010 FOLIO 1375

Between:
Glory Wealth Shipping Pte Limited
Claimants/Charterers/Section 69 Applicants
and
Korea Line Corporation
Respondents/Owners/ Section 69 Respondents

Mr Charles Priday (instructed by Winter Scott LLP) for the Applicants

Mr David Lewis (instructed by DLA Piper UK LLP) for the Respondents

Hearing dates: 22 June 2011

Mr Justice Blair
1

This appeal arises out of the collapse in the market experienced by the shipping industry in the wake of the financial crisis. By an award dated 26 October 2010, an arbitral Tribunal consisting of Mr Bruce Buchan and Mr Patrick O'Donovan awarded the Owners of the M.V. Wren damages for repudiatory breach by the Charterers of a Charterparty dated 22 February 2008 which led to its termination in November 2008. The issue is as to the measure of damages. By order of 4 April 2011, Burton J gave the Charterers leave to appeal under s. 69 Arbitration Act 1996 on the following question:

"What is the correct measure of damages for a charterer's repudiation of a time charter where there is, at the date of the termination of the charter, no market for the unexpired period and such a market only revives at a much later date?"

2

The vessel was a new-build which was delivered into charter on 21 June 2008. The Charterparty was a time charter on an amended NYPE form for a minimum of 36 months to maximum 38 months at a daily rate of US$39,800. In November 2008, the Charterers purported to make early redelivery, which the Owners accepted as a repudiatory breach entitling them to terminate the Charterparty. The dispute was referred to LMAA arbitration, and the Charterers subsequently conceded that their conduct had amounted to a repudiatory breach, leaving the issue of damages to be determined.

3

It was common ground that at the time of the termination of the contract in November 2008, there was no available market for a period charter of a duration that corresponded to the balance of the Charterparty. So the question was how the Owners' loss was to be calculated. They claimed damages on what was called a "hybrid basis", originally by reference to losses on a substitute fixture the vessel had contracted in the spot market up to January 2009, and by reference to market rates for the balance of the charter period from that time. In the course of the arbitral proceedings, and reflecting the Owners' expert evidence as to market conditions, the claim was amended. The amended claim was calculated on the basis of voyage charters which the vessel entered into up to 26 July 2009, and market rates of hire from that date. (The Charterers point out that when actual trading from January to July 2009 is taken into account, the Owners' claim reduced by approximately US$4.47m.)

4

As regards the revival of the market, which is the factual issue at point in the present case, the Owners' case was that as of June or July 2009, the market for the equivalent of the unexpired period of the charter (two years at that stage) had come back to life. The Charterers argued to the contrary that it had not revived. It was not in dispute that (whatever the true position as regards the revival of the market) the Owners had not in fact fixed the vessel on a long term charter at that time, continuing to fix her on the spot market.

The arbitrators' Award

5

The findings of the arbitrators as regards the market were as follows. The two year market in June and July 2009 "was no doubt in the early stages of recovery and was no doubt fragile, with the increase in activity…tentative at best. That does not mean, however, that there was no two year market at that point.…we took the view that there would have been a charterer of sufficient standing to take the vessel for two years at US$15,200.00 per day net had the Owners decided to so fix her". The arbitrators concluded, therefore, that there was an available market at the time in question, and their findings of fact are of course not challenged.

6

The submissions of the parties were essentially the same as they have been before the court on the appeal. In circumstances where there is no available market initially, but an available market arises later, there is, the Owners argued, no principled reason why a hybrid claim cannot best fulfil the object of an award of damages. The decision not to take advantage of that market in July 2009 was an independent business decision of the Owners—it did not follow that they could not recover market-based damages from that time. Otherwise, an innocent claimant would have to wait until the end of the repudiated charter before being able to make a full recovery.

7

The Charterers submitted that it was wrong in law to bring a hybrid claim for part actual and part market-based losses on the supposed basis that one looks to the market when it comes back to life. The only relevant date for the market is the date of termination, because this is the moment at which the innocent party can go into the market and mitigate its loss by finding a substitute fixture: see The Elena D'Amico [1980] 1 Lloyd's Rep 85 at 89. Where there is no available market at the date of termination, it is necessary to fall back on the broader question of asking what sum would put the claimants in the same financial position that they would have been in had the charterparty been performed. Since the Owners did not enter the long-term period charter market in July 2009, their actual trading thereafter must be the basis of the damages claim.

8

The core of the arbitrators' reasoning is in paragraphs 38 to 42 of the Award. They did not agree with the Charterers that, in principle, the Owners could not put forward a hybrid damages claim based on both actual and market losses in relation to the unexpired period of the charter. In stipulating that damages for the balance of a repudiated charter be assessed against the rate of a time charter of a duration equivalent to that balance, the law intends to facilitate comparison in so far as possible on a "like-for-like" basis. Had there been an identifiable market for a 30-month time charter at the time it was terminated, that would have been the yardstick used to calculate damages. As it was, there was no market at that point, and for the time being damages had to be established by using the net daily income, charter hire or time charter equivalent from charters actually performed. Given the law's preference for the use of the market rate for a period equivalent to the unexpired period of the charter, it was logical that once a viable market could be identified, that would become the criterion for determining loss.

9

The arbitrators explained that they were satisfied that the market-based approach to damages is favoured because it allows damages to be quantified relatively quickly after a repudiatory breach, so that there can be an end to litigation within a reasonable time. They agreed with the Owners that in the case of a lengthy unexpired charter period, calculation of damages on the basis of actual loss will be unsatisfactory. They accepted that there was an element of artificiality in that approach, but it was no more artificial than the principle that in cases of repudiatory breach, if there is at the time of termination an available market, damages will generally be assessed on the difference between the contract rate for the balance of the charterparty period and the market rate for the chartering in of a substitute vessel for that period. The same was true of the Charterer's suggestion of artificiality because the daily income from single voyages over a period may exceed the daily return from a time charter of comparable duration. The arbitrators did not accept that any allowance was to be made for trading vicissitudes.

10

In conclusion:

"Having decided that the Owners were entitled to advance a claim for both actual and market damages and that there was an available market, albeit fragile, at the relevant time, we awarded the Owners the full amount of their claim for damages for the balance of the charter period…with a deduction for accelerated payment."

Under this head of claim, the arbitrators awarded US$15,698,591.45, and it is only this element of the total award of US$22,823,858.90 which is challenged. I am told that nothing has yet been paid.

11

To appreciate the arbitrators' reasoning, it is necessary to appreciate the case as it was put to them. On the one hand, the Owners submitted that once the market revived, actual losses were to be put on one side, and damages were to be measured by reference to market rates for a "like-for-like" replacement two year time charter (that being the period that the repudiated Charterparty would have had to run at that point in time). The Charterers, on the other hand, submitted that the "available market measure" only applies where there is an available market at the time of termination. It cannot be applied where there is no available market, in which case one has to ask what loss has been caused to the claimant.

12

This explains the circumstances in which the arbitrators applied The Elena D'Amico principle as from the time the market revived, and it is clear that they did so as the best practical means of resolving the dispute they had to decide. The question is whether they were entitled to do so as a matter of law. Both counsel are agreed that this raises a point of principle. They are also agreed that the same questions arose for decision, whether the issue be expressed in terms of the question in respect of which Burton J gave the Charterers leave to appeal under s. 69 Arbitration Act 1996 (which I have set out at the beginning of this judgment), or in terms of the Owners' alternative formulation (which...

To continue reading

Request your trial
5 cases
  • Fulton Shipping Inc. of Panama (Respondents/Owners) v Globalia Business Travel S.A.U. (Formerly Travelplan S.A.U.) (Appellants/Charterers)
    • United Kingdom
    • Court of Appeal (Civil Division)
    • 21 December 2015
    ...Lloyd's Rep 75 for the correct approach where there was an available market and to The Kildare [2011] 2 Lloyd's Rep 360 and The Wren [2011] 2 Lloyd's Rep 370 for the approach where there was no available market namely, that the loss was to be determined by reference to the actual trading of......
  • Spar Shipping as v Grand China Logistics Holding (Group) Company, Ltd
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 18 March 2015
    ...market: Zodiac Maritime Agencies Ltd v Fortescue Metals Group Ltd (The Kildare) [2011] 2 Lloyd's Rep 360; Glory Wealth Shipping Pte v Korea Line Corporation (The Wren) [2011] 2 Lloyd's Rep 370. Each is an application of the principles I have endeavoured to 227 GCL invoked support for its ......
  • Sharp Corporation Ltd v Viterra B.v (Previously known as Glencore Agriculture B.v)
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 18 February 2022
    ...to be made of what the innocent party has lost, and a line thereby to be drawn under the transaction: see per Blair J in The Wren [2011] 2 Lloyd's Rep. 370 at [18]. The notional substitute contract 51 Bunge does contain dicta which suggest that the notional substitute contract must be on t......
  • Lewis Holdings Limited v Steel & Tube Holdings Limited
    • New Zealand
    • High Court
    • 11 September 2015
    ...(1906) 4 CLR 672. Gigi Entertainment Pty Ltd v Schmidt [2013] NSWCA 287. See Glory Wealth Shipping Pty Ltd v Korea Line Corporation [2011] EWHC 1819 (Comm), [2012] 1 All ER (Comm) 402; and Golden Straight Corporation v Nippon Yusen Kaisha (The Golden Victory) [2007] UKHL 12, [2007] 2 AC 353......
  • Request a trial to view additional results
3 firm's commentaries
  • The 'NEW FLAMENCO'
    • United Kingdom
    • Mondaq UK
    • 31 December 2015
    ...his loss. The Court, therefore, held that the arbitrator was right to rely on The Kildare [2011] 2 Lloyd's Rep 360 and The Wren [2011] 2 Lloyd's Rep 370. In The Kildare, there was no available market at the time of the repudiation, but the market later revived. However, only the actual trad......
  • The Relevance Of A Revival Of The Market To The Assessment Of Damages
    • United Kingdom
    • Mondaq United Kingdom
    • 6 October 2011
    ...Wealth Shipping Pte Limited v. Korea Line Corporation (M/V Wren) [2011] EWHC 1819 (Comm) Following the collapse of the shipping market in 2008, there were many instances of vessels under time charter being redelivered early by charterers who found themselves tied in to a financially unprofi......
  • Mitigation and the assessment of damages on early redelivery – “The New Flamenco”
    • United States
    • LexBlog United States
    • 2 March 2016
    ...the decision in a sale of goods context and mitigation more generally [3] [1980] 1 Lloyd’s Rep 75 [4] [2011] 2 Lloyd’s Rep 360 [5] [2011] 2 Lloyd’s Rep 370 [6] Derived from the leading case of British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railways Co of Londo......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT