Rainy Sky SA and Others v Kookmin Bank

JurisdictionEngland & Wales
JudgeLORD PHILLIPS,LORD KERR,LORD CLARKE,LORD WILSON,LORD MANCE
Judgment Date02 November 2011
Neutral Citation[2011] UKSC 50
Date02 November 2011
CourtSupreme Court
Rainy Sky S. A. and Others
(Appellants)
and
Kookmin Bank
(Respondent)

[2011] UKSC 50

before

Lord Phillips, President

Lord Mance

Lord Kerr

Lord Clarke

Lord Wilson

THE SUPREME COURT

Michaelmas Term

On appeal from: [2010] EWCA Civ 582

Appellants

Mark Howard QC

Michael Ashcroft

(Instructed by Ince & Co LLP)

Respondent

Guy Philipps QC

QC James Cutress

(Instructed by Linklaters LLP)

Heard on 27 July 2011

LORD CLARKE, (WITH WHOM LORD PHILLIPS, LORD MANCE, LORD KERR AND LORD WILSON AGREE)

Introduction and factual background
1

This appeal raises a short question of construction of shipbuilder's refund guarantees given pursuant to six shipbuilding contracts ("the Contracts"). The Contracts, which were all dated 11 May 2007, were between each of the first to sixth claimants ("the Buyers") and Jinse Shipbuilding Co Ltd ("the Builder"). Under the Contracts the Builder agreed to build and sell one vessel to each of the Buyers. The price of each vessel was US$33,300,000, payable in five equal instalments of US$6,660,000 due at specified points of time, with the final instalment payable on delivery. 1 By Article X.8 of the Contracts it was a condition precedent to payment by the Buyers of the first instalment that the Builder would deliver to the Buyers refund guarantees relating to the first and subsequent instalments in a form acceptable to the Buyers' financiers. As envisaged by Article X.8, by letter dated 22 August 2007 the respondent, Kookmin Bank ("the Bank"), issued six materially identical "Advance Payment Bonds" ("the Bonds"), one to each of the Buyers. The seventh claimant ("the Assignee") is the assignee of the benefit of the Bonds.

2

On 29 August 2007, the Buyers each paid the first instalment of US$6,660,000 due under the Contracts. On 29 September 2007, the first claimant paid the second instalment of US$6,660,000 under the contract to which it is a party.

3

In 2008 the Builder experienced financial difficulties and in late January 2009 it entered into and/or became subject to a debt workout procedure under the Korean Corporate Restructuring Promotion Law 2007. On 25 February 2009 the Buyers wrote to the Builder notifying it that this development triggered Article XII.3 of the Contracts and demanding an immediate refund of all the instalments paid, together with interest at 7% per annum. The Builder refused to make any refund on the ground that Article XII.3 of the Contracts had not been triggered as alleged. The dispute between the Buyers and the Builder has been submitted to arbitration pursuant to Article XIV.3 of the Contracts.

4

On 23 April 2009, the Buyers wrote to the Bank demanding repayment under the Bonds of the instalments paid under the Contracts. The Bank refused to pay. It did so initially on the ground that it was not obliged to pay pending resolution of the dispute between the Buyers and the Builder. That argument was subsequently rejected by Simon J ("the Judge") and there was no appeal to the Court of Appeal against that part of his order: [2009] EWHC Civ 2624 (Comm). The Bank subsequently raised a separate, and logically prior, argument that, on their true construction, the Bonds did not cover refunds to which the Buyers were entitled pursuant to Article XII.3 of the Contracts.

5

That argument was also rejected by the Judge, who gave summary judgment for the Assignee, but succeeded in the Court of Appeal, which gave summary judgment for the Bank against the Buyers and the Assignee. In the Court of Appeal Sir Simon Tuckey agreed with the Judge but the majority, comprising Thorpe and Patten LJJ, held the Bank's argument to be correct: [2010] EWCA Civ 582. The orders of the Judge and the Court of Appeal were made on 29 October 2009 and 27 May 2010 respectively. The Court of Appeal refused permission to appeal.

6

The Buyers appeal to this Court pursuant to permission granted by the Court. The issue is whether, on the true construction of paragraph 3 of the Bonds, the Buyers are entitled to payment under the Bonds in respect of refunds to which they are entitled under Article XII.3 of the Contracts. No-one suggested that the successful parties should not have summary judgment in their favour.

The Bonds
7

I begin with the Bonds because it was common ground that all depends upon the true construction of the Bonds and that the terms and meaning of the Contracts are only relevant to the extent that they inform the true construction of the Bonds. The paragraphs in the letter comprising the Bonds were not numbered but both the Judge and the Court of Appeal referred to them by number for convenience of reference and I will do the same. As so numbered the relevant parts of each Bond were these:

"[1] We refer to the … Contract entered into between … the Builder and yourselves for the construction and delivery of … the 'Vessel' to be delivered before [31 July 2009]. Other terms and expressions used in this Bond shall have the same meaning as in the Contract, a copy of which has been provided to us.

[2] Pursuant to the terms of the Contract, you are entitled, upon your rejection of the Vessel in accordance with the terms of the Contract, your termination, cancellation or rescission of the Contract or upon a Total Loss of the Vessel, to repayment of the pre-delivery instalments of the Contract Price paid by you prior to such termination or a Total Loss of the Vessel (as the case may be) and the value of the Buyer's Supplies delivered to the Shipyard (if any) together with interest thereon at the rate of … (7%) per annum (or … (10%) per annum in the case of a Total Loss of the Vessel) from the respective dates of payment by you of such instalments to the date of remittance by telegraphic transfer of such refund.

[3] In consideration of your agreement to make the pre-delivery instalments under the Contract and for other good and valuable consideration (the receipt and adequacy of which is hereby acknowledged), we hereby, as primary obligor, irrevocably and unconditionally undertake to pay to you, your successors and assigns, on your first written demand, all such sums due to you under the Contract (or such sums which would have been due to you but for any irregularity, illegality, invalidity or unenforceability in whole or in part of the Contract) PROVIDED THAT the total amount recoverable by you under this Bond shall not exceed US $[26,640,000] … plus interest thereon at the rate of … (7%) per annum (or … (10%) per annum in the case of a Total Loss of the Vessel) from the respective dates of payment by you of such instalments to the date of remittance by telegraphic transfer of such refund.

[4] Payment by us under this Bond shall be made without any deduction or withholding, and promptly on receipt by us of a written demand (substantially in the form attached) signed by two of your directors stating that the Builder has failed to fulfil the terms and conditions of the Contract and as a result of such failure, the amount claimed is due to you and specifying in what respects the Builder has so failed and the amount claimed. Such claim and statement shall be accepted by us as evidence for the purposes of this Bond alone that this amount claimed is due to you under this Bond.

[5] Our liability under this Bond shall not be affected by … (v) any insolvency, re-organisation or dissolution of the Builder, or (vi) any other matter or thing which may operate to discharge or reduce our liability hereunder.

…"

8

The Bonds further provided that they were assignable, that they were governed by English law and that all disputes arising out of them were to be determined by the Commercial Court.

9

The resolution of the issue between the parties depends upon the true construction of paragraph [3]. The Bank promised to pay on demand "all such sums due to you under the Contract". The question is what was meant by "such sums". Only two possibilities were suggested. The Buyers said (and the Judge and Sir Simon Tuckey held) that the expression "such sums" referred back to the "pre-delivery instalments" in the first line. They said that the purpose of the Bond was to guarantee the refund of pre-delivery instalments and that the promise was therefore to refund pre-delivery instalments. By contrast the Bank said (and Thorpe and Patten LJJ held) that the expression "such sums" was a reference back to the sums referred to in paragraph [2], namely the repayment of the pre-delivery instalments paid prior to a termination of the Contract or a Total Loss of the vessel and the value of the Buyer's Supplies in the case of a Total Loss. On the Buyers' analysis the Bond guaranteed pre-delivery instalments which were repayable under Article XII.3 in the case of any insolvency event, whereas on the Bank's analysis it did not.

The Contracts
10

It is common ground that the terms of the Contracts are relevant to the true construction of the Bonds. They are referred to in the Bonds and provide the immediate context in which the Bonds were entered into. They are thus plainly an important aid to the meaning of the Bonds.

11

Article X of the Contracts provided, so far as material as follows:

"ARTICLE X: PAYMENT

5. REFUND BY THE BUILDER

The payments made by the Buyer to the Builder prior to delivery of the Vessel shall constitute advances to the Builder. If the Vessel is rejected by the Buyer in accordance with the terms of this Contract, or if the Buyer terminates, cancels or rescinds this Contract pursuant to any of the provisions of this Contract specifically permitting the Buyer to do so, the Builder shall forthwith refund to the Buyer in US dollars, the full amount of total sums paid by the Buyer to the Builder in advance of delivery together with interest thereon as herein provided within thirty (30) banking days of acceptance of rejection.

… The interest rate of the refund … shall be seven per cent (7%) per annum …

If the Builder is required to refund...

To continue reading

Request your trial
962 cases
  • Enterprise Inns Plc v (1) Palmerston Associates Ltd (2) Paul Rigby and Another
    • United Kingdom
    • Chancery Division
    • 30 November 2011
    ...but, even if it had been, that would not have changed the definition of Specified Beers in paragraph 1 of the current Terms of Trading. The Rainy Sky 45 I have set out the parties' submissions in a little detail as they identify the matters which require to be dealt with on the way to reach......
  • Hyundai Merchant Marine Company Ltd v Americas Bulk Transport Ltd M.v "pacific Champ"
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 8 March 2013
    ...not even begin to consider — as a matter of construing the words — replacing the words agreed upon: Rainy Sky SA v Kookmin Bank [2012] 1 Lloyd's Rep 34 [21]–[23]; City Alliance Ltd v Oxford Forecasting Services Ltd [2001] 1 All ER (Comm) 233, at [12]–[13]. c) Further, any ambiguity in the m......
  • Aberdeen City Council v Stewart Milne Group Ltd
    • United Kingdom
    • Supreme Court (Scotland)
    • Invalid date
    ...appeal should be dismissed. 28 In the course of argument some reference was made to the recent decision of the Supreme Court in Rainy Sky SA v Kookmin Bank [2011] UKSC 50; [2011] 1 WLR 2900. That appeal was concerned with the role of commercial good sense in the construction of a term in ......
  • Flynn & Benray Ltd v Breccia & McAteer
    • Ireland
    • High Court
    • 13 August 2015
    ...caution in the use of "business common sense" in the interpretation of commercial contracts. They refer to Rainy Sky SA v. Kookmin Bank [2011] 1 WLR 2900 where Lord Clarke at para. 21 stated that:- 287 "The language used by the parties will often have more than one potential meaning. I woul......
  • Request a trial to view additional results
45 firm's commentaries
  • Complex Commercial Litigation Law Review – England and Wales
    • United Kingdom
    • JD Supra United Kingdom
    • 27 January 2021
    ...v. West Bromwich Building Society [1997] UKHL 28, Chartbrook Ltd v. Persimmon Homes Ltd [2009] UKHL 38 and Rainy Sky SA v. Kookmin Bank [2011] UKSC 50.21 Wood v. Capita Insurance Services Ltd [2017] UKSC 24 and MT Hojgaard A/S v. E.ON Climate and Renewables UK Robin Rigg East Ltd [2017] UKS......
  • Complex Commercial Litigation Law Review - Fifth Edition - England & Wales
    • United Kingdom
    • JD Supra United Kingdom
    • 19 December 2022
    ...v. West Bromwich Building Society [1997] UKHL 28, Chartbrook Ltd v. Persimmon Homes Ltd [2009] UKHL 38 and Rainy Sky SA v. Kookmin Bank [2011] UKSC 50.21 Wood v. Capita Insurance Services Ltd [2017] UKSC 24 and MT Hojgaard A/S v. E.ON Climate and Renewables UK Robin Rigg East Ltd [2017] UKS......
  • Contractual interpretation disputes from the Trustee's perspective: The saga continues
    • United Kingdom
    • JD Supra United Kingdom
    • 23 June 2016
    ...([2009] 1 AC 1101), Re Sigma Finance Corporation ("Sigma") ([2010] 1 All ER 571), Rainy Sky SA v Koomkin Bank ("Rainy Sky") ([2011] 1 WLR 2900), Napier Park European Credit Opportunities Fund Limited v Harbourmaster Pro-Rata CLO 2 BV ([2014] EWCA Civ 984), Arnold v Britton ([2015] 2 WLR 159......
  • Quinn Emanuel Business Litigation Report -- January 2012
    • United States
    • JD Supra United States
    • 17 January 2012
    ...for the purposes of subsequent enforcement proceedings. Common Sense and Contract Interpretation: In Rainy Sky SA v. Kookmin Bank [2011] UKSC 50, The U.K. Supreme Court recently gave important guidance on the English courts’ approach to contractual interpretation. The fundamental rule under......
  • Request a trial to view additional results
23 books & journal articles
  • Case Notes on Contracts of Guarantee
    • Ireland
    • Hibernian Law Journal No. 12-2013, January 2013
    • 1 January 2013
    ...IEHC 93 (unreported, High Court, Kelly J, 27 March 2012), pp.33–39 (in particular paras.49–52) and Rainy Sky SA & Orsd v Kookmin Bank [2011] UKSC 50, [2011] WLR 2900 05 Cuddihy.indd 81 11/06/2013 13:46 82 KAROLE CUDDIHY This follows from the decision of the House of Lord in Wickman Machine ......
  • Meaning and Construction of Certain Restrictive Covenants which Impact on the Development and Commercial Use of Land
    • United Kingdom
    • Wildy Simmonds & Hill Restrictions on the Use of Land Part IV. Restrictive covenants (freehold land)
    • 30 August 2016
    ...Europe Ltd v Powell [2014] EWCA Civ 437; Martin v David Wilson Homes Ltd [2004] EWCA Civ 1027 at [14]. 4 Rainy Sky SA v Kookmin Bank [2011] UKSC 50, [2011] 1 WLR 2900 at [23]. 5 Attorney General of Belize v Belize Telecom Ltd [2009] UKPC 10, [2009] 1 WLR 1988 (Privy Council) at [16]–[27] (L......
  • Security for performance
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...Meredith Projects Pty Ltd v Fletcher Construction Pty Ltd [2000] NSWSC 493 at [46]–[54], per Rolfe J. 91 Rainy Sky SA v Kookmin Bank [2011] 1 WLR 2900 at 2906–2907 [14], per Lord Clarke JSC (considering the interpretation of a shipbuilder’s refund guarantees). See also Lam Hong Leong Alumin......
  • Clauses 'Defining the Risk as a Whole' and 'Risk Mitigation' Clauses under Section 11 of the Insurance Act 2015: The Shifting Tide of Crewing Warranties in Marine Insurance
    • United Kingdom
    • Southampton Student Law Review No. 12-1, January 2022
    • 1 January 2022
    ...2.12. 94 The general observations on principles of construction in the judgment of the Supreme Court in Rainy Sky Ltd v Kookmin Bank [2011] 1 W.L.R. 2900, delivered by Lord Clarke, have also to be taken into account here. 95 Kler Knitwear Ltd v Lombard General Insurance Co Ltd [2000] Lloyd'......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT