Triumph Controls – UK Ltd v Primus International Holding Company

JurisdictionEngland & Wales
JudgeMrs Justice O'Farrell
Judgment Date11 March 2019
Neutral Citation[2019] EWHC 565 (TCC)
CourtQueen's Bench Division (Technology and Construction Court)
Docket NumberCase No: HT-2016-000104
Date11 March 2019

[2019] EWHC 565 (TCC)

IN THE HIGH COURT OF JUSTICE

BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES

TECHNOLOGY AND CONSTRUCTION COURT (QBD)

Royal Courts of Justice

Strand, London, WC2A 2LL

Before:

Mrs Justice O'Farrell DBE

Case No: HT-2016-000104

Between:
(1) Triumph Controls – UK Limited
(2) Triumph Group Acquisition Corporation
Claimants
and
(1) Primus International Holding Company
(2) Primus International Inc.
(3) Primus International Cayman Co
Defendants

Rajesh Pillai & Nathaniel Bird (instructed by Reynolds Porter Chamberlain LLP) for the Claimants

Edward Pepperall QC & Helen Gardiner (instructed by Harrison Clark Rickerbys Limited) for the Defendants

Reading dates: 13 th & 14 th June 2018

Hearing dates: 18 th, 19 th, 21 st, 22 nd, 25 th, 26 th, 27 th, 28 th June 2018 2 nd, 3 rd, 5 th, 9 th, 10 th, 11 th, 12 th, 13 th, 17 th, 18 th & 19 th July 2018

Approved Judgment

I direct that pursuant to CPR PD 39A para 6.1 no official shorthand note shall be taken of this Judgment and that copies of this version as handed down may be treated as authentic.

Mrs Justice O'Farrell

Part 1 — Background

Paragraphs 1 – 96

The Share Purchase Agreement

66 – 87

The Dispute

88 – 96

Part 2 – Notice of Claims

Paragraphs 97 – 128

Clause 20 Service

102 – 111

Proper notice of nature and amount claimed

112 – 121

Clause 6.6 claim

122 – 128

Part 3 – Nadcap Warranty Claims

Paragraphs 129 – 247

Nadcap Issues

177

Warranty 6.1

178 – 193

Accreditation at time of completion

194 – 199

Manipulation of the 2012 Audit

200 – 225

Reasons for the 2013 failure

226 – 237

Impact of loss of Nadcap accreditation

238 – 244

Warranty 6.2

245 – 246

Conclusion

247

Part 4 – Operational Warranties Claim

Paragraphs 248 – 356

Delivery and quality issues

251 – 252

Operational warranty claim issues

305 – 306

Material contracts

307 – 313

Knowledge for the purpose of clause 8.2

314 – 317

Breach of the warranties

318 – 326

Disclosure

327 – 352

Completion Accounts

353 – 355

Conclusion

356

Part 5 – FLP Claim

Paragraphs 357 – 482

FLP Issues

395 – 397

Documents forming the FLPs

398 – 399

Scope of the warranty

400 – 402

Were the FLPs carefully prepared?

403 – 463

What should carefully prepared FLPs have shown?

464 – 470

Would Triumph have walked away from the acquisition of Primus or would the purchase price have been lower?

471 – 481

Conclusion on FLPs

482

Part 6 – Clause 6.6 Claim

Paragraphs 483 – 485

Part 7 – Quantum

Paragraphs 486 – 496

Part 8 — Conclusion

Paragraphs 497 – 498

Mrs Justice O'Farrell
1

The claimants (“Triumph”) are subsidiaries of Triumph Group, Inc. (“TGI”), a multinational aerospace and defence manufacturer and service provider based in Pennsylvania, USA.

2

The defendants (“Primus”) are subsidiaries of Precision Cast Parts Corporation (“PCC”), a multinational manufacturer of complex metal components.

3

On 27 March 2013 Triumph and Primus entered into a share purchase agreement (“the SPA”) whereby Triumph purchased the share capital of three Primus companies. The purchased companies, based in Farnborough, UK, and Rayong, Thailand, manufacture composite and metallic components for the aerospace industry.

4

The purchase price paid by Triumph under the SPA was US$ 76,530,145.

5

In these proceedings Triumph claims damages limited to US$ 63,530,145 in respect of alleged breaches of warranty, namely:

i) the loss of Nadcap accreditation in respect of the Farnborough facility (“the Nadcap Claim”);

ii) undisclosed delivery and quality problems at Farnborough (“the Operational Warranty Claim”);

iii) failure by Primus to prepare financial projections with care (“the FLP Claim”); and

iv) failure by Primus to notify Triumph of the claimed breaches of warranty (“the Clause 6.6 Claim”).

6

Primus disputes the claims on the grounds that:

i) the alleged breaches of warranty are denied;

ii) Triumph failed to give adequate notice of the claims;

iii) it is denied that causation has been established; and

iv) the basis and valuation of quantum is disputed.

The aerospace manufacturing industry

7

The design, testing and final assembly of aircraft for supply to ultimate customers is carried out by prime contractors (“Primes”), also known as Original Equipment Manufacturers (“OEMs”). The OEMs operate production lines on which aircraft are assembled in large hangars.

8

Tier 1 suppliers are responsible for integrating and delivering substantial components of the aircraft, such as engines, major structural parts and avionics systems to OEMs for final assembly.

9

Tier 2 suppliers manufacture and supply components to Tier 1 suppliers for further integration into major components but do not have design responsibility. The Primus companies in Farnborough and Thailand purchased by Triumph are Tier 2 suppliers.

10

Tier 3 suppliers manufacture and provide individual parts and components.

11

Tier 4 suppliers supply materials and processing services.

12

The aerospace industry is highly competitive and OEMs are required to meet tight delivery schedules to deliver completed aircraft to their customers. As a result, OEMs demand similar timescales from their supply chains. The tight schedules and lean manufacturing approach, under which limited stocks of parts are held, creates pressure on the supply chain to meet delivery schedules and achieve the required product quality.

Composite material production at Farnborough

13

Composite materials are a combination of two or more materials, usually a sheet of resin and a reinforcement matrix. In the aerospace industry, composites are used because they are stronger, stiffer, lighter, more durable and can be more easily moulded into different shapes than their metal equivalents.

14

The most common composites used in the aerospace industry are carbon fibre reinforced plastic (“CFRP”) and glass reinforced plastic (“GRP”). Carbon or glass fibres are woven into fabric and impregnated with a polymer resin, commonly polyester or epoxy, which acts as the bonding agent (known as “pre-preg” material). The pre-preg material is moulded into the desired shape and cured to form a solid component.

15

The Farnborough composites division facility of Primus specialises in three types of processes for the production of composites: hand lay-up, metal bond and compression moulding. The key steps in the production of composite parts at Farnborough can be summarised as follows.

16

Uncured composite manufacturing raw materials, such as pre-preg material, film adhesives and compounds, are kept in cold storage pending requirement. Each material has a specified storage temperature, to avoid deterioration of the material affecting the cure or bonding process, and a specified maximum shelf life, typically between 6 and 24 months. When it is ready to be used, the composite material is defrosted. Once defrosted, the frozen shelf life is replaced by a maximum working life. Any unused material can be re-frozen or chilled as specified and the working shelf life is reduced accordingly.

17

The defrosted rolls of flat film adhesive, resin impregnated glass or carbon fibre fabric pre-preg material are rolled out on a cutting table and cut to the required shape for ply lay-up. The cut plies are then placed into heat sealed plastic bags and refrozen for storage. The cutting process must be carried out in a controlled contamination area (“CCA”). The CCA maintains a positive air pressure to ensure that particles of dirt are pushed out of the room and away from the exposed material. The entrance to the CCA is fitted with an airlock and there is a clean filtered air supply, controlling temperature and humidity, to maintain the integrity of the uncured materials.

18

Some component parts require thicker sections for strength, rigidity or acoustic attenuation requirements. Such composites are achieved by the use of a honeycomb material, normally metallic or Nomex, a paper honeycomb coated in resin, that is sandwiched within the composite structure. The honeycomb is machined using circular table saws or routing tools and tool block guides to trim and create the necessary profile of the material. This task must be carried out in an environmentally monitored area (“EMA”), an area where contaminants detrimental to adhesion and bonding may be restricted and where basic environmental conditions such as temperature and humidity may be monitored. In addition, segregation of the metallic honeycomb from Nomex is required in order to avoid contamination by foreign objects which could affect bond strength. Honeycombs are usually degreased after machining and placed in heat sealed bags.

19

At Farnborough some of the composite assemblies comprise aluminium alloy clad metallic sheet parts. These require anodising and priming before bonding in the composite structure. During the anodising process, a thin anodic layer is deposited on the aluminium surface through electrolysis in a bath of chromic acid. After anodising, the parts are sent to the priming booth for spray application of primer to the bonding surfaces. Following curing of the primer, the anodised and primed parts are placed in protective bags before delivery to the clean room for assembly.

20

Before honeycomb is laid up into the composite structure, a film adhesive is applied to the bonding surfaces (reticulation). This is performed in a CCA environment. Backing film is removed from the adhesive and laid on the honeycomb surface. Heaters on a beam are passed slowly over the honeycomb and resin film, placed on a wire frame support. The heated resin film flows into the ends of the core...

To continue reading

Request your trial
4 cases
  • MDW Holdings Ltd v James Robert Norvill
    • United Kingdom
    • Chancery Division
    • 4 May 2021
    ...and scope of the matter disclosed”, and (iii) it is disclosed “in or under the Disclosure Letter”. 223 In Triumph Controls UK Limited v Primus International Holding Company [2019] EWHC 565 (TCC), which involved a clause materially similar to clause 7.6 in the SPA, O'Farrell J considered th......
  • Decision Inc. Holdings Proprietary Ltd v Stephen Garbett
    • United Kingdom
    • Chancery Division
    • 16 March 2023
    ...parties to settle without recourse to litigation)”. 191 However, in Triumph Controls – UK Ltd v Primus International Holding Company [2019] EWHC 565 (TCC), O'Farrell J pointed out that the requirement is for clarity rather than precision — she considered that this did not require “full det......
  • Equitix Eeef Biomass 2 Ltd v Michael Fox
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 27 September 2021
    ...at arm's length in a tense negotiation. This was common sense and supported by the cases: Triumph Controls Ltd v Primus International [2019] EWHC 565 (TCC) at [486] (O'Farrell J); Sycamore Bidco Ltd v Breslin [2012] EWHC 3443 (Ch) at [391] (Mann J); Ageas (UK) Ltd v Kwik-Fit (GB) Ltd [201......
  • Tactus Holdings Ltd v Philip Mark Jordan
    • United Kingdom
    • King's Bench Division (Commercial Court)
    • 1 March 2024
    ...concerning the construction of disclosure clauses of this sort in Triumph Controls UK Ltd v Primus International Holding Company [2019] EWHC 565 (TCC) (O'Farrell J) at [335]: “i) The commercial purpose of such disclosure clauses is to exonerate the seller from its breach of warranty by fai......
4 firm's commentaries
3 books & journal articles
  • Price and payment
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...(Sales) Pty Ltd (No.5) [2016] QSC 199 at [138]–[154], per Flanagan J. 1240 Triumph Controls UK Ltd v Primus International Holding Co [2019] EWhC 565 (TCC) at [98], per O’Farrell J (and see also, in the same proceedings, Triumph Controls UK Ltd v Primus International Holding Co [2019] EWhC 2......
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...UK Ltd v primus International holding Co [2018] EWhC 176 (TCC) III.26.109 Triumph Controls UK Ltd v primus International holding Co [2019] EWhC 565 (TCC) II.6.327, II.6.330, II.13.127 Triumph Controls UK Ltd v primus International holding Co [2019] EWhC 2216 (TCC) II.6.327 Triumph Controls ......
  • Damages
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...Co Ltd [2018] EWhC 1 (TCC) at [436], per Sir antony Edwards-Stuart; Triumph Controls UK Ltd v Primus International Holding Co [2019] EWhC 565 (TCC) at [240], per O’Farrell J. In he “Sivand” , hobhouse LJ held that such recoverable costs incurred in mitigation could include costs paid to the......

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT