Benaim (UK) Ltd v Davies Middleton & Davies Ltd

JurisdictionEngland & Wales
Judgment Date15 June 2005
Neutral Citation[2005] EWHC 1370 (TCC)
Docket NumberNo.HT-05–71
CourtQueen's Bench Division (Technology and Construction Court)
Date15 June 2005
Between
Benaim (Uk) Ltd.
Claimant/Applicant
and
Davies Middleton & Davies Ltd.
Defendant/Respondent

[2005] EWHC 1370 (TCC)

Before

His Honour Judge Peter Coulson Q.C.

No.HT-05–71

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

TECHNOLOGY & CONSTRUCTION COURT

St. Dunstan's House

MR. DAVID SEARS Q.C. (instructed by Berrymans Lace Mawer) appeared on behalf of the Applicant/Claimant.

MR. STEPHEN FURST Q.C. (instructed by Burges Salmon, Bristol) appeared on behalf of the Respondent/Defendant.

(As Approved by the Judge)

CONTENTS OF JUDGMENT

A INTRODUCTION

Paras 1–4

B THE SUBSTANTIVE DISPUTE

Paras 5–10

C THE ARBITRATION

Paras 11–14

D THE AWARD

Paras 15–21

E THE APPLICATION UNDER SECTION 24: REMOVAL

Paras 22–49

The Relevant Sections of the 1996 Act

22–26

The Basis of the Application to Remove the Arbitrator

27–28

The Complaint

29–32

The Ambit of the Hearing in January and March 2004

33–42

The Arbitrator's Findings

43–46

The Arbitrator's Conduct

47–48

Summary on Delay

49

F THE APPLICATION UNDER SECTION 68: SERIOUS IRREGULARITY

Paras 50–104

The Relevant Sections of the 1996 Act

50

Serious Irregularity

51–60

Substantial Injustice

57–61

Ground 1/Buildability

62–67

Ground 2/The Length of the Deviator Block

68–73

Ground 3/Mr. Hambly's Inexperience

74–75

Ground 4/The Reason for the Change in Design 76–83

a) Point Not Put to Mr. Brennan

78–80

b) Mr. Nicholson's Evidence

81

c) Absence of Reasons

82–83

Ground 5/The Finite Element Analysis

84–87

Ground 6/No Detailed Weight Calculation

88

Ground 7/The Design of the Reinforcement

89

Ground 8/Delay

90

Ground 9/ Miscellaneous Allegations

91–93

Ground 10/Failure To Provide Reasons

94–103

a) The Detail of the Award

98

b) The Caveat in the Award

99–100

c) The Nature of the Questions

101–103

Summary/Serious Irregularity

104

G THE APPLICATION UNDER SECTION 69: APPEAL

Paras 105–158

The Relevant Section of the 1996 Act

105–106

Question of Law

107–109

Obviously Wrong

110

Just and Proper for the Court to Determine

111–112

Ground 1/Schedule of Principal Quantities

113–139

a) To Whom Was The Obligation Owed

114–121

b) Absolute Obligation or Skill and Care

122–127

c) Comparison with The Final Design

128–131

d) Criticism Based on Increased Quantities

132–126

e) The Lack of Modifications Between ADP and TDP

137–139

Ground 2/Failure to Carry Out a Strut and Tie Calculation

140–144

Ground 3/Failure to Check the Layout of the Pre-Stress

145–148

Ground 4/The Negligent Design of the Reinforcement

149–153

Ground 5/Delay

154–158

H CONCLUSIONS

159–160

HIS HONOUR JUDGE PETER COULSON QC:

A INTRODUCTION

1

By an Arbitration Claim Form issued on the 21 st March 2005 the Claimant, Benaim (UK) Ltd., referred to throughout the papers as RBA, seeks a number of remedies arising out of an interim Award dated the 21 st February 2005. The Award was produced by an Arbitrator, Mr. Peter Chapman, the Second Defendant in these proceedings. The arbitration had been commenced against RBA by Davies Middleton & Davies Ltd., in administrative receivership, referred to throughout as DMD, and centred on complaints by DMD about RBA's management of the design process of the new A13 viaduct in Dagenham. The Award, which did not concern quantum, was very largely in DMD's favour and contained a number of important findings against RBA.

2

In these proceedings RBA seek an order removing the Arbitrator under s.24 of the Arbitration Act 1996 ("the 1996 Act") on the grounds that he failed properly to conduct the proceedings leading up to the Award and, as a result, caused RBA substantial injustice. Further and in the alternative, RBA seek permission to apply to set aside the award pursuant to s.68 of the 1996 Act on the grounds of serious irregularity, including the Arbitrator's alleged failure to comply with the general duty imposed upon him by s.33 of the Act. Finally, RBA seek permission to appeal on certain questions of law arising out of the award pursuant to s.69 of the Act. The parties are agreed that, in respect of the orders sought pursuant to ss.68 and 69, both the applications for permission, and the substantive applications, should be dealt with together.

3

Following the exchange of evidence between RBA and DMD—the Arbitrator has chosen not to play an active part in these proceedings—there was a hearing before me on the 10 th and 11 th June 2005. The majority of that time was taken up with the parties' submissions on the linked applications under ss.24 and 68 of the 1996 Act. Although there is a considerable amount of material before the Court, I have been greatly assisted in considering these applications by the clear analysis adopted by both Mr. Sears Q.C. for RBA, and Mr. Furst Q.C. for DMD.

4

I propose therefore to set out briefly the substantive dispute between the parties (Section B below) and the history of the arbitration (Section C). I set out some of the key passages of the Award in Section D. I then go on to deal with each of the three applications in turn in a sequence which is different to that adopted by the parties during the course of argument. This is because, in my judgment, on an application of this sort, it is logical to take the application under s.24 first (Section E), since, if the Arbitrator is removed, that is the end of the arbitration for all practical purposes. Next I consider the application to set aside the Award as a result of the allegations of serious irregularity under s.68 (Section F below) since that application, if successful, would render the Award, or substantial parts of it, a nullity. Only then do I turn to consider the appeal under s.69 (Section G below) because that application assumes the continued role of the Arbitrator and an extant Award, and is simply designed to ensure that the Award is remitted to the Arbitrator on particular questions. A short summary of my conclusions is set out at Section H below.

B THE SUBSTANTIVE DISPUTE

5

Together with Tarmac Construction Ltd ("TCL"), DMD and RBA were involved (in their different ways) in tendering for and carrying out the design and construction of the A13 viaduct in Dagenham. This major civil engineering project comprised a six-lane elevated viaduct structure that crossed a number of roads and railway lines as well as the vast Ford assembly plant.

6

The intention was that TCL would construct the substructure of the viaduct, in particular the foundations and piers; DMD would construct the superstructure of the viaduct, in particular the pre-cast concrete segments; and RBA would design both the substructure and the superstructure. However, it is important to note that the main contract for the design and construction of the entire project was always going to be between the Secretary of State for Transport, as the employer, and TCL, as the main contractor. In essence, therefore, DMD were the proposed subcontractors to TCL in respect of the superstructure and RBA were the proposed subcontractors to TCL and DMD in respect of the design.

7

After at least one earlier design, referred to as the ADP, RBA produced a Tender Design Proposal ("TDP") in respect of the viaduct, which was accepted by the Highways Agency on the 20 th August 1996. RBA also produced a Schedule of Principal Quantities ("SPQ") which was intended to identify and quantify the works encompassed within the TDP. DMD produced a fixed price tender for the superstructure work based on the TDP and SPQ, which was accepted by TCL, who in turn submitted a fixed price tender for the whole of the design and construction works to the Highways Agency. On the basis of that tender TCL were then engaged by the Secretary of State for Transport on the 30 th August 1996 to design and construct the viaduct.

8

As is common in the construction industry, the legal relationships between TCL, DMD and RBA were not formalised until a later stage. On the 17 th June 1997 DMD entered into a Joint Venture Agreement ("JVA") with TCL, pursuant to which they agreed to design and construct the superstructure of the viaduct for £14,951,461.44. On the same date DMD and TCL entered into a Design Agreement with RBA pursuant to which RBA agreed to carry out a range of services relating to the design of the viaduct. Both contracts were expressly made retrospective and therefore covered some elements of work and services, such as RBA's production of the TDP and the SPQ, which had already been performed.

9

It was DMD's case in the arbitration that the problems began in about November 1996 when, at a meeting on the 7 th November, RBA's representatives told Mr. Davies of DMD that the TDP was not buildable. DMD also relied on RBA's letter of the 13 th January 1997, which referred to a number of changes to the TDP as offering "the most economic and buildable solution for this project".

10

It is common ground between the parties that the TDP was changed in a variety of ways in late 1996 and early 1997. The issue between the parties was how and why those changes came about. It was DMD's case that, effectively, the changes had resulted from inherent inadequacies within the TDP and, since their tender had been based upon that TDP, they had suffered losses of £5 million or more as a result. It was RBA's case that there was nothing wrong with the TDP and the changes that occurred were part of usual design development.

C THE ARBITRATION

11

DMD commenced...

To continue reading

Request your trial
12 cases
  • The Islamic Republic of Pakistan v Broadsheet LLC
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 12 Julio 2019
    ...with Compton. The authorities which were referred to in the judgment in Compton did not relate to section 68 (with the exception of Benaim (UK) Ltd [2005] EWHC 1370 which the judge declined to follow). 20 The issues for this court are therefore: i) Can “inadequate reasons” (as such term is ......
  • Pace Shipping Company Ltd v Churchgate Nigeria Ltd
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 7 Octubre 2010
    ... ... 422 at paragraph 8, Benaim v Davies [2005] All ER (D) 104 at paragraphs 94–96 and ... ...
  • Martrade Shipping & Transport GmbH v United Enterprises Corporation: The Wisdom C
    • United Kingdom
    • Queen's Bench Division (Commercial Court)
    • 12 Junio 2014
    ...Funding Corpn v Medfinco Ltd [2003] EWHC 1798 (Ch); [2004] 1 Lloyd’s Rep 652Benaim (UK) Ltd v Davies Middleton & Davies Ltd (No 2) [2005] EWHC 1370 (TCC); 102 Con LR 1Care Shipping Corpn v Itex Itagrani Export SA (The Cebu) [1993] QB 1; [1991] 3 WLR 609; [1992] 1 All ER 91; [1990] 2 Lloyd’s......
  • Andrew Martin v Michael Harris
    • United Kingdom
    • Chancery Division
    • 23 Julio 2019
    ...principle wrongly”. This bold statement is said to be supported by a number of authorities, one of which was supplied to me – Benaim v Davies Middleton [2005] EWHC 1370. This is a decision of HHJ Peter Coulson QC (as he then was) which in part dealt with an application for permission to app......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT