Jawaby Property Investment Ltd v Interiors Group Ltd and another

JurisdictionEngland & Wales
JudgeThe Hon. Mrs Justice Carr DBE
Judgment Date16 March 2016
Neutral Citation[2016] EWHC 557 (TCC)
Docket NumberCase No: HT 2016 000063
CourtQueen's Bench Division (Technology and Construction Court)
Date16 March 2016

[2016] EWHC 557 (TCC)

IN THE HIGH COURT OF JUSTICE

QUEEN'S BENCH DIVISION

TECHNOLOGY AND CONSTRUCTION COURT

Royal Courts of Justice

Strand, London, WC2A 2LL

Before:

The Hon. Mrs Justice Carr DBE

Case No: HT 2016 000063

Between:
Jawaby Property Investment Limited
Claimant
and
(1) The Interiors Group Limited
First Defendant
(2) Andrew Stephan George Black
Second Defendant

Mr Anthony Speaight Q.C. (instructed by Eversheds LLP) for the Claimant

Mr James Bowling (instructed by Fenwick Elliott LLP) for the Defendants

Hearing dates: 9th March 2016

The Hon. Mrs Justice Carr DBE

Introduction

1

By this Part 8 claim the Claimant ("JPIL") seeks declaratory relief against the First Defendant ("TIG") in relation to certain payment obligations under a construction contract entered into between JPIL and TIG ("the Contract") for works at Holborn Tower, High Holborn, London WC1 ("the Property") and a related Escrow Agreement ("the Escrow Agreement"). JPIL is the current freehold owner of the Property, which is a high rise office block.

2

JPIL initially also sought injunctive relief against TIG and the Second Defendant ("Mr Black"), TIG's sole director, to restrain him from signing and to restrain TIG from presenting a statutory declaration so as to trigger payment from an Escrow Account ("the Escrow Account") the subject of the Escrow Agreement.

3

The sum in issue is £1,109,214.09. TIG is currently unable to pay to its subcontractors monies properly due to them. If payment is released, then Mr Black expects the company to continue and to continue successfully. But it cannot survive without the receipt of these monies. There is evidence of financial difficulties on the part of TIG in the past. JPIL suggests that TIG's current financial difficulties cannot be attributable, at least not exclusively, to non-payment by JPIL. There is a real "insolvency risk" that any payment received by TIG will be used to pay creditors unrelated to the Contract. TIG is currently subject to a winding-up petition presented by an unpaid creditor. A hearing of that petition has been adjourned from 8 th March 2016. In these circumstances, this matter has proceeded as a matter of urgency and on an expedited basis.

4

The ultimate question for the Court is whether there has been a "default" within the meaning of the Escrow Agreement. JPIL contends that TIG is not entitled to trigger payment from the Escrow Account on two grounds:

a) A valuation sent by TIG by email for Valuation 7 on 7 th January 2016 ("the Valuation") was not a valid Interim Application within the meaning of Clause 4.8.1 of the Contract;

b) Alternatively, if, contrary to JPIL's case, the Valuation was a valid Interim Application, then an email and attachments sent by Ashford Property Services Limited ("APS"), JPIL's Agent under the Contract, on 18 th January 2016 ("the 18 th January email") constituted a valid Pay Less Notice as required under clause 4.9 of the Contract and was served not later than 5 days before the final date for payment.

5

JPIL seeks final declarations reflecting the above. It is apparent from this that, whilst Mr Black is joined to the proceedings for the purpose of injunctive relief, the substantive dispute is between JPIL and TIG. Equally, given that JPIL seeks final declaratory relief to the effect that there has not been a default event under the Contract, JPIL's claim for injunctive relief effectively falls away. There is no suggestion that, this dispute having arisen, TIG has taken steps to make a call on the Escrow Account, despite the straitened circumstances in which it finds itself. JPIL realistically does not pursue its claim for injunctive relief in the circumstances.

6

TIG regards JPIL's objections as spurious excuses to deny TIG payment of monies, if necessary from the Escrow Account. Its position is that it made a valid Interim Application in response to which no valid Pay Less Notice was served. It seeks a mandatory injunction requiring payment of the monies from JPIL or alternatively from the Escrow Account.

7

Evidence on the claim has been served as follows:

a) For JPIL: statements from Mr Jonathan Bowley of JPIL's solicitors, Eversheds LLP ("Eversheds"), and Mr Christopher Millican of APS;

b) For TIG: a statement from Mr Black.

8

To the extent that the parties have attempted to go into the wider merits of their disputes under the Contract, I ignore such matters for present purposes. Mr Millican, for example, goes into significant detail on the accuracy of the Valuation, suggesting that it is a gross overvalue. This is not accepted by TIG. Such matters are either not relevant or not suitable for consideration in this limited Part 8 procedure. Additionally, there is a degree of factual dispute as to whether or not there was an agreed system between the parties for the purposes of Interim Applications under the Contract, namely as to what was an acceptable form and manner of interim payment application. Mr Black says that there was. Mr Millican says that there was no agreement to alter the payment provisions in the Contract. APS simply followed the pragmatic course of fitting in as best it could with what TIG was choosing to do. Neither party suggested that there should be cross-examination, or that the claim should be taken outside the Part 8 procedure (although TIG made it clear that, were I to find that the issues could not be concluded properly within the procedure, I should find against JPIL). So far as the witness evidence is concerned, I proceed below on the basis of such evidence as is not contested. Thus, for example, it has not been disputed by JPIL that APS requested TIG to prepare summary sheets in a certain way after Valuation 4, and TIG complied with that request. Beyond that, I proceed on the basis of what the documents themselves show.

The Contract

9

The Contract was entered into originally between Tekxel Limited ("Tekxel") and TIG on 31 st July 2015 for the refurbishment of the ground and main reception, and floors 2, 3, 4, 6, 7, 8 and 11 of the Property. The contract was novated subsequently from Tekxel to JPIL. It was on the standard JCT 2011 Design and Build Contract Conditions with amendments. The works are split into ten sections, with each section having a sectional completion date and rate of liquidated damages for late completion. Works to floors 1 and 10 were added as a variation. The Contract sum was £4,077,966.78.

10

By Article 3, save to the extent that JIPL might otherwise specify by notice to TIG, APS has " full authority to receive and issue applications, consents, instructions, notices, requests or statements and otherwise to act for [JPIL] under any of the Conditions".

11

By Article 14 TIG's obligations are conditional on an Escrow Agreement in an agreed form being executed by the parties and Eversheds LLP, solicitors formerly acting for Tekxel and now for JPIL, confirming that the Minimum Deposit Balance had been deposited in the Escrow Account. Such confirmation was given.

12

Clause 1.7 (as amended) provides materially as follows:

" Any notice, approval, request or other communication to be given by either Party under this Contract shall be sufficiently served if sent by hand, by fax or by post to the registered office, or if there is none then the last known address of the Party to be served…"

13

Clauses 4.8 to 4.10 (as amended) provide materially as follows:

" Contractor's Interim Applications and Due Dates

4.8.1 In relation to each Interim Application, the Contractor shall make an application to the Employer (an 'Interim Application') in accordance with the following provisions of this clause 4.8, stating the sum that the Contractor considers to be due to him and the basis on which that sum has been calculated…

4.8.3 Where Alternative B applies, for the period up to practical completion of the Works, Interim Applications shall be made as at the monthly dates specified in the Contract Particulars for Alternative B up to the date of practical completion or the specified date within one month thereafter. Subsequent Interim Applications shall be made at intervals of 2 months (unless otherwise agreed), the last such application being made upon the expiry of the Rectification Period or, if later, the issue of the Notice of Completion of Making Good (or, where there are Sections, the last such period or notice). The due date in each case shall be the later of the specified date and the date of receipt by the Employer of the Interim Application.

4.8.4 Interim Applications may be made before, on or after completion of the relevant stage or the monthly date and shall be accompanied by such further information as may be specified in the Employer's Requirements.

Interim Payments – final date and amount

4.9.1 The final date for payment of an Interim Payment shall be 30 days from its due date.

4.9.2 Not later than 5 days after the due date the Employer shall give a notice (a "Payment Notice") to the Contractor in accordance with clause 4.10.1 and, subject to any Pay Less Notice given by the Employer under clause 4.9.4, the amount of the Interim Payment to be made by the Employer on or before the final date for payment shall be the sum stated as due in the Payment Notice.

4.9.3 If the Payment Notice is not given in accordance with clause 4.9.2, the amount of the Interim Payment to be made by the Employer shall, subject to any Pay Less Notice under clause 4.9.4, be the sum stated as due in the Interim Application.

4.9.4 If the Employer intends to pay less than the sum stated as due from him in the Payment Notice or Interim Application, as the case may be, he shall not later than 5 days before the final date for payment give the Contractor notice of that intention in accordance with clause 4.10.2 (a "Pay Less Notice"). Where a Pay Less Notice is given, the payment to be made on or before the...

To continue reading

Request your trial
8 cases
  • Zvi Construction Company LLC v The University of Notre Dame (USA) in England
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 2 August 2016
    ...from The Law of Waiver, Variation and Estoppel, 3 rd ed., 2012, Wilken & Ghaly (which was also adopted by Carr J. in Jawaby Property Investment Ltd v The Interiors Group Ltd [2016] EWHC 557 (TCC)) as a useful summary of the law: "(i) It is not enough that the common assumption upon which th......
  • Grove Developments Ltd v S&T(UK) Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 27 February 2018
    ...or not a particular pay less notice is valid: see, for example, paragraph 43 of the judgment of Carr DBE J in Jawaby Property Investment Limited v The Interiors Group Limited [2016] EWHC 557 (TCC)5. It is then instructive to see the effect of that approach in the TCC cases concerned with th......
  • Kersfield Developments (Bridge Road) Ltd v Bray and Slaughter Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 18 January 2017
    ...Coulson J at Para.37; Henia Investments Inc v Beck Interiors Limited [2015] EWHC 2433 per Akenhead J at Para.17; Jawaby Property Investment Limited v The Interiors Group Limited [2016] EWHC 557 per Carr J. at Paras.39–43. An interim application must be obviously identifiable as such and it ......
  • Surrey and Sussex Healthcare NHS Trust v Logan Construction (South East) Ltd
    • United Kingdom
    • Queen's Bench Division (Technology and Construction Court)
    • 13 January 2017
    ...Modular Ltd v Mar City Developments Ltd [2015] BLR 694, Henia Investments Inc. v Beck Interiors Ltd [2015] BLR 704 and Jawaby Property v The Interiors Group Ltd [2016] BLR 328. In the present case, it was submitted that Logan had not been open and transparent about its intentions. Mr Crook ......
  • Request a trial to view additional results
3 firm's commentaries
  • Projects And Construction Law Update - April 13, 2016
    • United Kingdom
    • Mondaq UK
    • 19 April 2016
    ...not been established or agreed. To read more, please click here. Jawaby Property Investment Ltd v The Interiors Group Ltd and another [2016] EWHC 557 (TCC) Here the employer Jawaby sought a declaration concerning payment obligations under the contract it entered into with a contractor, Inte......
  • Payment Provisions In Construction Contracts: Another Year On
    • United Kingdom
    • Mondaq UK
    • 5 December 2016
    ...Contract, 2005 edition, revision 2, 2009 8 [2016] EWHC 168 (TCC) 9 The Scheme for Construction Contracts 10 [2016] EWHC 241 (TCC) 11 [2016] EWHC 557 (TCC) This article is taken from Fenwick Elliott's 2016/2017 Annual Review. To read further articles go to The content of this article is inte......
  • Serving contractual notices: wrong method, right result
    • United Kingdom
    • JD Supra United Kingdom
    • 20 February 2017
    ...ineffective, even if the method is not explicitly included in the contract. In Jawaby Property Investment Ltd v The Interiors Group [2016] EWHC 557 (TCC), the court concluded that a contractor’s interim payment application had been validly served by email even though the contract expressly ......
5 books & journal articles
  • Contract administration
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...J (considering the JCT Standard Building Contract Without Quantities 2011); Jawaby Property Investment Ltd v he Interiors Group Ltd [2016] EWHC 557 (TCC) at [42]–[43], per Carr J. ContraCt aDMiniStration the contractual requirements relating to both its form and to the circumstances when it......
  • Price and payment
    • United Kingdom
    • Construction Law. Volume II - Third Edition
    • 13 April 2020
    ...v Waco UK Ltd [2015] eWHc 1400 (tcc) at [28]–[30], per edwards-Stuart J; Jawaby Property Investment Ltd v he Interiors Group Ltd [2016] eWHc 557 (tcc) at [45]–[46], per carr J. 468 prICE aND paYMENT completion. here is, however, no reason in principle why a contract could not permit progres......
  • Table of cases
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...I.2.51, I.2.57, I.2.70, I.2.82 Jaura v ahmed [2002] EWCa Civ 210 III.26.311 Jawaby property Investment Ltd v he Interiors Group Ltd [2016] EWhC 557 (TCC) I.3.90, I.5.129, II.6.59, II.6.61, II.6.234, II.6.235, III.20.96 Jaya Sarana Engineering pte Ltd v GIB automation pte Ltd [2007] SGhC 49 ......
  • Contract terms
    • United Kingdom
    • Construction Law. Volume I - Third Edition
    • 13 April 2020
    ...712); Tesco (Ireland) Ltd v Mofett [2015] NIQB 68 at [13], per Weatherup J; Jawaby Property Investment Ltd v he Interiors Group Ltd [2016] EWHC 557 (TCC) at [48]–[49], per Carr J (considering clause 1.7 of the JCT 2011 Design and Build Contract Conditions (with amendments)); Torbey Investme......
  • Request a trial to view additional results

VLEX uses login cookies to provide you with a better browsing experience. If you click on 'Accept' or continue browsing this site we consider that you accept our cookie policy. ACCEPT